Argentum AI, Kyndryl sign $630M Boulder data center deal
Argentum AI and Kyndryl are deploying Nvidia B300 systems for AI inference at a 10 MW Tier III site in Boulder, Colorado under a 20-year, $630 million agreement.
Key takeaways
- Argentum AI and Kyndryl announced a 20-year, $630 million collaboration on Tuesday, Nov. 17.
- The initial scope covers 10 megawatts at Kyndryl’s Tier III facility in Boulder, Colorado.
- Nvidia B300 systems are being deployed for AI inference, with deployment under way.
- $31.5 million per year is an even-spread average; no payment schedule was disclosed.
- Kyndryl reported $3.65 billion in quarterly revenue; as of Nov. 18, EDGAR showed no related 8-K.

By Rebecca Stone
Argentum AI and Kyndryl signed a 20-year data center collaboration valued at $630 million on Tuesday, Nov. 17, starting with 10 megawatts of capacity at Kyndryl’s Tier III facility in Boulder, Colorado.
The GPU cloud provider is deploying Nvidia B300 systems at the site for AI inference, and the companies said deployment is under way. The announcement disclosed neither the number of GPUs in the project nor a completion date for the initial 10-megawatt phase.
What does the $630 million agreement cover?
- Contract term and value: 20 years and $630 million.
- Initial capacity: 10 megawatts at Kyndryl’s Tier III site in Boulder.
- Systems and workload: Nvidia B300 systems for AI inference.
- Deployment status: Under way, according to the companies.
Spread evenly, the $630 million contract value averages $31.5 million a year. The release provides no payment schedule, so that average is not guidance for annual cash receipts or Kyndryl’s recognized revenue. It also does not allocate the value among hardware, facility capacity, power or services.
The release calls the arrangement a data center collaboration and does not identify the contract type, included services or price per megawatt. That makes $630 million a headline value rather than a fully specified revenue schedule, even though the agreement has a defined term and an initial capacity figure.
Kyndryl reported $3.65 billion in revenue in its most recent quarter. That company-wide figure establishes operating scale, but it does not identify revenue from the collaboration or its timing. The announcement provides no revenue-recognition schedule or price per megawatt.
The phase is concrete but its technical scale remains open. The Tier III designation identifies facility class, but it does not specify rack count, B300 configuration, cooling design or redundancy. With no GPU count, 10 megawatts also cannot be converted into accelerator units or a stated inference throughput. That leaves the commercial relationship clearer in duration than in near-term output.
Revenue timing is equally open. Even if the $630 million were paid evenly, an average does not say when money moves. The announcement does not say whether payments are tied to construction, staged capacity additions or recurring operating services.
Who occupies the Boulder facility?
The release says the facility welcomes “a fast-growing, enterprise-grade AI inference company” as its “flagship anchor tenant,” but it does not name that company. Argentum is the named deployer in the B300 collaboration, yet the release does not explicitly identify it as the quoted tenant. That leaves the anchor tenant’s identity and any allocation of the initial capacity unconfirmed.
“Partnering with an established technology services and infrastructure provider like Kyndryl is an important milestone for Argentum AI,” said founder and CEO Andrew Sobko. The statement frames the arrangement around Kyndryl’s services and infrastructure role. Separately, the companies said they intend to broaden the collaboration, but they gave no target scope, added megawatts, products or timetable.
What has Kyndryl disclosed?
As of Nov. 18, Kyndryl’s filing list on EDGAR showed no Form 8-K concerning the agreement. Its latest 8-K, filed Nov. 4, covered quarterly results. At that cutoff, the report found no deal-specific current report to corroborate or qualify the announcement’s $630 million value, 20-year term or initial 10-megawatt scope.
What should buyers watch next?
The next disclosures matter because the announcement leaves several operating and financial variables open:
- GPU count and hardware configuration behind the initial 10 megawatts.
- Installation and commissioning dates.
- Payment cadence and revenue-recognition treatment.
- Tenant roster and scope of the broader collaboration.
The next commercial test is whether the initial 10 megawatts reaches operation with Nvidia B300 systems and whether the planned broader collaboration adds capacity, services or tenants. Until the GPU count, payment schedule and completion date emerge, $31.5 million a year remains an arithmetic average, not a forecast of Kyndryl revenue.