AWS Kozani Campus: Four Buildings, 240 MW IT Load, 1 GW Option

A Greek environmental filing shows AWS's Kozani campus at four buildings, 20 data halls and 240 MW of IT load, with PPC investing €1bn and a 1 GW expansion option held until May 2027.

By Tom Whitfield584 words

Key takeaways

  1. AWS's Kozani campus will have 300 MW power capacity, 240 MW IT load, four buildings and 20 data halls.
  2. PPC invests €1 billion; AWS contributes a similar amount for IT infrastructure.
  3. The 300 MW grid agreement is expected to finalize by Q1 2027; construction runs summer 2027 to end of 2028.
  4. AWS holds exclusivity on a 1 GW expansion option until May 2027.
  5. Annual cooling water use is estimated at about 203,000 cubic meters.
AWS's Kozani campus in Greece will have four buildings, 20 data halls and 240 MW of IT load, filing shows
AWS's Kozani campus in Greece will have four buildings, 20 data halls and 240 MW of IT load, filing shows — analogicus / pixabay

Amazon Web Services' planned data center campus in Kozani, Greece, will deliver 300 MW of power capacity and 240 MW of IT load across four buildings and 20 data halls, according to an environmental impact assessment first reported by Greek outlet OT.gr and detailed by Data Center Dynamics. The filing also confirms the site could scale to 1 GW, giving AWS a path to one of the larger cloud footprints in southeastern Europe.

AWS is developing the project with Public Power Corporation (PPC) at the former Agios Dimitrios coal-fired power plant, once Greece's largest, which shut down earlier this year. The repurposing of a decommissioned coal site for hyperscale compute is the core of the commercial logic: the land, the grid connection and the cooling water are already in place.

What does the filing show?

The campus covers roughly 45 hectares. The four identical buildings total 77,360 square meters and stand 36 meters tall. Each building houses five data halls, for 20 in total across the site.

Power will come from the existing 400 kV substations at Agios Dimitrios, reached through two new underground cable lines. The connection reuses transmission capacity originally built for the 1.55 GW coal plant, which is what makes a 300 MW first phase feasible on a retired industrial site rather than a greenfield location.

Cooling is hybrid. Between 60% and 90% of the cooling load will use water, depending on weather conditions, with the balance air-cooled. Annual water consumption is estimated at about 203,000 cubic meters. The takeaway: the design leans on the plant's legacy water infrastructure while keeping a dry-cooling fallback for hot spells.

Who pays what, and when?

PPC is investing €1 billion in the project, and AWS is expected to contribute a similar amount for IT infrastructure, DCD reported. That split places the land and power partner and the cloud operator on roughly equal financial footing.

The timeline in the filing is specific:

  • PPC expects grid connection terms soon; the 300 MW agreement should be finalized by the first quarter of 2027.
  • Equipment orders would follow the signed agreement.
  • Construction is hoped to begin in summer 2027 and finish by the end of 2028.
  • AWS holds exclusivity on the 1 GW expansion option until May 2027.

The exclusivity clause is the number to watch. If AWS exercises the 1 GW option before May 2027, Kozani moves from a large regional deployment to a gigawatt-class campus on a timeline that would extend well past the 2028 completion date for phase one.

Why Greece, and why now?

AWS currently has no cloud region in Greece. Its only in-country presence is a Local Zone in Athens, opened in July 2026. A 240 MW campus in Kozani would be a step change in AWS's Greek infrastructure and would tie the country's cloud capacity to a former coal town in the northwest rather than to the capital.

For PPC, the project converts a stranded asset — a 1.55 GW coal plant closed amid Greece's energy transition — into anchor demand from a hyperscale tenant, with roughly €1 billion of investment on each side. For AWS, it secures power and land at a moment when both are the binding constraints on data center growth in Europe.

If the grid agreement closes on schedule in the first quarter of 2027, construction could start within months, putting the first 240 MW of IT capacity in service by the end of 2028.

mlq.ai (Source)

Filed under

Share this article:

More from Tom Whitfield

Tom Whitfield

Show full bio

Staff writer covering companies, deals and strategy in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,224 articles

Read also

« Previous articleNext article »