Cameron County halts SpaceX tax break for $24B data center
Cameron County’s 3-2 vote Nov. 17 stopped the first step on SpaceX’s $24 billion data center tax request, but Starbase still has a separate city hearing set for Dec. 9.
- By
- Rebecca Stone
- Filed
By Rebecca Stone
Cameron County commissioners voted 3-2 on Nov. 17 to halt county consideration of SpaceX’s request for a property-tax abatement for a proposed $24 billion data center and natural-gas power plant near the Port of Brownsville, Texas. The application covers a 444-acre site in the City of Starbase.
The vote rejected publishing a formal notice and scheduling a public hearing, the first procedural step toward a county tax break. The action stopped the county process before SpaceX could obtain a hearing, rather than recording a final decision on the merits of the abatement.
County Judge Eddie Treviño Jr. and Precinct 2 Commissioner Joey Lopez voted to advance the request. Lopez told KRGV he wanted to review the numbers first, but said: “as of right now, there won’t be a second meeting. So the [request] is dead.”
What did SpaceX ask the county to approve?
SpaceX sought a 100% property-tax abatement for 10 years, according to Newsweek citing The Brownsville Herald. Its county application listed:
- $24 billion in capital investment
- $13.8 billion in first-year taxable value
- 500 new jobs
SpaceX filed the request Oct. 15 and submitted a revised application Nov. 9 for the 444-acre site. Those three figures described the company’s proposal. They did not confirm that the full capital investment had been spent, that taxable value had been realized or that the 500 positions had been filled.
The $24 billion label also requires care. It came from SpaceX’s application and describes a proposed capital investment; neither the county vote nor the state permit documents that the money has been spent. Likewise, the $13.8 billion first-year taxable value is an application figure tied to the abatement request, not a confirmed county property-tax base.
The chronology runs from the Oct. 15 filing to the Nov. 17 vote, with a revision on Nov. 9 and a state permit on Nov. 16 in between. The tax application and permit moved on separate schedules, and neither established that construction had started or that the power plant was operating.
More than a dozen speakers opposed SpaceX’s request during public comment on Nov. 17, the Rio Grande Guardian reported. Newsweek said it had asked SpaceX for comment and was awaiting a response when it published its report. Its account therefore carried no company answer to the objections or the vote.
What remains open after the county vote?
The county action does not end SpaceX’s separate abatement request to the City of Starbase. The city scheduled a public hearing for Dec. 9. The municipal path remains open.
The Dec. 9 agenda concerns only the city’s request; its abatement percentage, term and projected tax-revenue effect were not disclosed. A scheduled hearing confirms procedural continuation, not approval.
The state air permit issued Nov. 16 covers 35 natural-gas turbines for 750 megawatts. It confirms a permitted design, not operating output, and the reports do not show that all 35 turbines have been built.
Neither the county filing nor the public reporting breaks the $24 billion investment into separate data-center and natural-gas power-plant costs. The available figures also do not state how much county property tax the requested 10-year, 100% abatement would forgo.
Public discussion therefore rests on the application’s aggregate investment, taxable value and job estimate, rather than a project-level cost schedule.
Starbase’s Dec. 9 hearing is the next scheduled opportunity to advance the separate abatement. The state permit documents authorization for 35 turbines totaling 750 megawatts, but construction, operating output, the proposed $24 billion spending and 500 jobs remain contingent.