Eisman: Local Permits, Not Chip Supply, Are the AI Trade's Biggest Risk
Eisman tells CNBC the biggest risk to the AI trade is local and state governments slowing data center permits, not chip supply, with a slowdown range of 10% to 30%.
- By
- Grace Kim
- Filed
- Channel
- AI & Compute
- Read
- 4 min read
Amazon spent $77.26 billion on capital expenditure in the third quarter of 2026, up 120% year over year, and still expects roughly $220 billion for the full year. AWS revenue grew 39%.
That spending now runs into a bottleneck that has little to do with silicon. On CNBC on November 17, 2026, Steve Eisman, the investor known as "Big Short," said the largest risk to the AI trade sits with local zoning boards and statehouses, ahead of chip supply.
What did Eisman say about the biggest AI risk?
Eisman framed the danger as a range rather than a single forecast. He said: "I think the biggest issues by far are how much are local and state governments going to slow AI data center construction? Is it going to be a 100% moratorium? That would obviously put the country into a recession overnight, or is it something like 10 to 30%?"
His range runs from a full freeze, which he called a recession trigger, to a 10% to 30% slowdown he treats as the more plausible case.
He also weighed reports about the leading AI chipmaker's sales in Southeast Asia, which he said could amount to around 15% of chip revenue: "That's a lot." Even so, he ranked permitting first. A GPU generates nothing until a powered building stands ready to hold it.
Why are towns blocking data centers?
A moratorium is a temporary pause on new permits, usually while a town or state rewrites rules on zoning, power or water. The objections come down to electricity, water and land.
A Colorado legislative staff memo notes that data centers require large amounts of electricity for computational power and water to cool the computer systems. It adds that laws covering land use, water use and protections for residential customers have already passed nationwide.
In House testimony, the American Public Power Association said the average individual data center load doubled from 150 megawatts to 300 megawatts between 2023 and 2024. The EIA puts average U.S. electricity demand growth at 2.1% per year over the last five years, after 15 flat years.
Where is the friction already changing siting?
On Digital Realty's third-quarter call, Chief Investment Officer Gregory Wright pointed to "numerous moratoriums across Michigan" and power queues in Ohio as reasons hyperscalers are moving into Indiana.
Digital Realty has 1.5 gigawatts under construction, with 63% already pre-leased. Its chief executive acknowledged: "Yes, there's always here and there a delay."
At Equinix, CEO Adaire Fox-Martin said: "Power availability, legislation and community sentiment have created some headwinds for the industry." She added that cancellations would make "already scarce capacity much more of a scarce resource." Equinix booked a record $533 million in annualized gross bookings, and its stock is up 36.94% year to date.
Who takes the first hit from a slowdown?
- Digital Realty: 1.5 gigawatts under construction, 63% pre-leased; 250 megawatts of pre-leased deliveries due over the next two quarters.
- Vertiv: third-quarter revenue rose 61.2% to $4.31 billion and organic orders more than doubled; the CEO said permitting and power are "pacing items, but they are not slowing down growth."
- Eaton: Electrical backlog up 46%.
- Constellation Energy: down 22.76% year to date.
The market has not treated that balance kindly. Over the past month, Vertiv fell 8.85% and Eaton dropped 13.76%. Constellation's CEO called the decline "a bit of an overreaction in the market to the election results based upon fear that Democrats won't let data centers get built."
Who wins if construction slows?
Eisman reversed the risk in the same interview. He said: "But longer term, I think if the AI data center construction story is 10 to 30% less, the group that makes out the best are the hyperscalers because they go cash flow positive."
Amazon is the case in point. It spent $77.26 billion on capex in the third quarter, up 120%, and still expects about $220 billion for 2026, with AWS revenue up 39%. A slowdown trims that spending while tight capacity supports pricing. Eisman said a slowdown would make construction "much more sustainable."
What three markers will settle the argument?
- FERC's ruling on colocation, which Constellation expects in the first half of next year.
- Whether Equinix delivers more than 13,000 cabinets in the fourth quarter.
- Digital Realty's 250 megawatts of pre-leased deliveries due over the next two quarters.
The debate over whether permitting or silicon binds the AI buildout now has a scoreboard. If the FERC ruling lands as Constellation expects and Equinix clears 13,000 cabinets in the fourth quarter, the 10% to 30% slowdown case firms up, and hyperscalers with funded capex and secured power take share from suppliers whose growth depends on construction volume.
Source: 247wallst.com
More from Grace Kim
Show full bio
Market editor covering people, launches and day-to-day practice in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.
1,099 articles
Related articles
eisman-warns-openai-failure-could-push-us-into-immediate-recession
Eisman Warns OpenAI Failure Could Push US Into Immediate Recession
ecb-names-ai-and-sovereign-debt-as-leading-financial-risks
ECB names AI and sovereign debt as leading financial risks
nasdaq-s-black-thursday-misses-the-point-nvidia-s-real-risk-is-jensen-huang
NASDAQ's 'Black Thursday' Misses the Point: Nvidia's Real Risk Is Jensen Huang
ai-data-center-boom-meets-capital-power-and-grid-constraints
AI Data Center Boom Meets Capital, Power and Grid Constraints