HSBC Sold $300 Million of Oracle's Project Jupiter Debt at 85 Cents

HSBC sold about $300 million of Oracle's Project Jupiter construction debt at roughly 85 cents on the dollar, sending Oracle shares down nearly 4% as AI data center financing comes under scrutiny.

By
Tom Whitfield
Filed
Channel
AI & Compute
Read
4 min read

HSBC sold roughly $300 million of construction debt tied to Oracle's Project Jupiter data center in New Mexico at a price in the mid-80s, according to a Bloomberg report published November 16. Oracle stock fell approximately 4% on the news, closing a two-day slide that has wiped out nearly 9% of the share price.

Oracle (NYSE: ORCL) traded at $114.34 at 12:05 p.m. ET on November 17, down 3.99% from Monday's $119.09 close. The shares had already declined 4.99% on Monday as lenders reassessed their exposure to large AI infrastructure projects.

What did HSBC actually sell?

The $18 billion construction financing was arranged in late 2025 by a syndicate of approximately 20 banks to fund Project Jupiter, an AI data center campus in Doña Ana County, New Mexico. The debt includes separate tranches tied to different buildings within the project.

HSBC's holding represented less than 2% of the overall package. Bloomberg, citing people familiar with the transaction, reported that the bank sold the exposure several weeks before the news became public, shortly after Oracle sent a force majeure notice to the project's developer, a unit of Blue Owl Capital. A price in the mid-80s means approximately 85 cents for each dollar of face value.

The discount does not automatically establish HSBC's realized accounting loss. That would depend on the bank's carrying value, initial fees and acquisition costs, none of which have been disclosed. HSBC declined to comment; Oracle had no immediate comment when Bloomberg sought a response.

The sale provides a harder data point than earlier secondary-market quotes. In September, Project Jupiter loans were quoted at approximately 89 to 91 cents on the dollar, according to Financial Times reporting. HSBC's executed exit came in below that range, though the two observations concern different dates and potentially different tranches.

The takeaway: a completed trade shows what one lender actually accepted to leave the project, not merely where dealers were marking the debt.

Why did Oracle declare force majeure?

Project Jupiter is designed to provide 2.45 gigawatts of computing infrastructure as part of the Stargate AI expansion associated with Oracle, OpenAI and SoftBank. The campus covers approximately 1,400 acres in southern New Mexico.

Development has encountered delays involving energy infrastructure, air-quality approvals and pipeline permits. In September, Oracle sent a force majeure notice to the Blue Owl-affiliated developer, seeking contractual protection against payment obligations if circumstances outside its control prevented the campus from becoming operational as expected.

Reuters reported on September 24 that Oracle sought to defer payments if delays prevented a 2028 opening, rather than abandoning its role as principal tenant. A source familiar with the contracts told Reuters that Oracle could not terminate the lease under any circumstances, and that Blue Owl had approximately $3 billion in equity committed, with Oracle responsible for the debt costs. The notice could extend the period during which Oracle pays lower development-stage rent. Blue Owl said the notice did not change the financial commitments of the multiyear development.

Construction delays can affect financing economics even when a project proceeds, because lenders wait longer for the development to generate its intended cash flows.

Are other banks pulling back?

In a separate report published November 17, the Financial Times said ING and Société Générale had offered up to $800 million of data center debt for sale in recent weeks, including financing tied to Oracle's Stargate projects.

  • ING's process includes approximately $500 million in loans linked to several data center operators and Project Jupiter.
  • Société Générale has sought buyers for approximately $300 million of project financing tied to Oracle's Project Lighthouse in Wisconsin and Project Frontier in Texas.

Loans tied to the Wisconsin and Texas projects were quoted above 90 cents on the dollar, while the New Mexico debt was expected to attract prices in the mid-80s, according to the FT. That spread suggests lenders are distinguishing between individual projects on construction progress and power availability, rather than applying one discount to all AI infrastructure lending. For banks, such sales can also be portfolio management — reducing concentration or freeing regulatory capital — rather than a judgment that the borrower will default.

How does this connect to Oracle's $20 billion raise?

The disclosure arrives two weeks after Oracle priced approximately $20 billion in common stock and senior notes, according to its November 2 announcement. The offering included 86.2 million shares at $116 each, alongside $10 billion in senior notes with coupons ranging from 7% to 8.65% and maturities extending from 2029 to 2046.

The corporate raise and the Jupiter construction loans are distinct instruments with different creditor protections, but both fund the same strategy: expanding computing capacity for major AI customers, particularly OpenAI. Oracle has reported approximately $664 billion in remaining performance obligations, yet that backlog does not remove execution risk in building the infrastructure to fulfill it.

HSBC's sale does not prove Oracle's AI strategy is failing, nor that AI debt faces a systemic crisis. It shows one lender accepted a meaningful discount to exit a development with documented permitting and power problems. Investors will now watch whether additional lenders sell at comparable discounts, and how Oracle's financing costs shape its ability to convert contracted cloud demand into cash flow.

Source: financefeeds.com

Share this article:

More from Tom Whitfield

Tom Whitfield

Show full bio

Staff writer covering companies, deals and strategy in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,054 articles

Related articles

« Previous article