AI & Compute · 4 min read
Mitsubishi Heavy CEO expects off-grid data centers to return to grid
Mitsubishi Heavy booked 8 GW of large-frame turbine orders in the first half of fiscal 2026 and holds a 37 GW backlog as its CEO expects costly off-grid gas plants to lose ground to utilities.
Key takeaways
- MHI booked 8 GW of large-frame gas turbine orders in the first half of fiscal 2026, versus 16 GW for all of fiscal 2025, with a 37 GW backlog.
- Utilities and IPPs accounted for 94% of MHI's new gas turbine orders in 2024 and 2025.
- MHI is spending about $3.1 billion on capacity and plans to double production by 2030 through automation at existing plants in the United States and Japan.
- Ito expects global gas turbine demand to average about 70 GW annually over the next five years.
- Ito says data centers account for around 10% of total U.S. electricity demand.

By Tom Whitfield
Off-grid power economics could send U.S. data centers back to utilities, while Mitsubishi Heavy Industries holds a 37 GW large-frame gas turbine backlog. The company is spending about $3.1 billion on manufacturing capacity and plans to double production by 2030.
Mitsubishi Heavy Industries CEO Eisaku Ito expects smaller on-site gas plants to cost more to run than the large plants utilities and independent power producers are building. Over the long term, he expects that gap to push data centers back onto the grid and support utility expansion. Utility Dive reported the comments on Nov. 23, based on a translated transcript of Mitsubishi Heavy's Nov. 6 analyst call.
Why would off-grid data centers return to the grid?
The proposed alternative to a grid connection relies on smaller dedicated gas-fired plants. Ito says those units have higher running costs than larger utility-scale plants, and he expects operators to favor grid power as the cost difference persists. The reported call did not provide a cost per megawatt-hour or a break-even point, so his claim remains a directional forecast rather than a quantified price comparison.
The mechanism is simple: smaller on-site generation carries the higher operating cost Ito described. Grid-connected utilities and IPPs can instead serve that load with the larger plants they are already building, giving their expansion plans a potential demand source.
Ito does not claim that off-grid gas is disappearing now; he describes long-term cost pressure toward grid connections. In plain terms, smaller dedicated plants lose to larger utility-scale generation.
Can data-center demand derail turbine growth?
Ito said: “Electricity demand from data centers is expected to grow rapidly in the United States,” but “data centers still account for only around 10% of the country's total electricity demand.” He also said broader electricity demand growth does not depend solely on data centers, making the sector a fast-growing slice rather than the whole market.
“If some of the anticipated growth in demand does not materialize, there will be some impact,” he said, but “we believe the effect on our overall GTCC business would be limited.” He thus accepts some downside from missing expected load while limiting its significance for Mitsubishi Heavy's gas turbine combined-cycle business.
Utilities and IPPs made up 94% of MHI's new gas turbine orders in 2024 and 2025. Utility Dive also reported that MHI had recorded no order cancellations in the past two years. A data-center slowdown would not, in Ito's view, overwhelm that broader utility and IPP order base.
What does MHI's order book show?
MHI booked 8 GW of large-frame gas turbine orders in the first half of fiscal 2026, compared with 16 GW for all of fiscal 2025. Its large-frame backlog stands at 37 GW. Because the first figure covers only half a year, the comparison with the full prior fiscal year does not establish a decline.
Orders in MHI's Energy Systems segment rose 16% from a year earlier, while segment profit rose 80%, helped by more orders and exchange rates. The segment includes gas turbines, nuclear power and aero engines, so those growth rates are broader than turbine-only results. Mitsubishi Heavy therefore has substantial order visibility, but its strongest segment-level growth figures cover more than turbines.
How much manufacturing capacity is MHI adding?
Ito expects global gas turbine demand to average about 70 GW a year over the next five years. He expects roughly 100 GW of sales across manufacturers in 2026 and described that level as exceptionally strong, adding that he did not expect it to last. These figures are management forecasts, not booked orders.
MHI is spending about $3.1 billion to add gas turbine manufacturing capacity and plans to double production capacity by 2030. Most of the increase will come through process improvements and automation at existing plants in the United States and Japan. Because the company gave no baseline for the doubling, the plan signals direction rather than a precise annual output; MHI is preparing for a strong near-term market without claiming the 2026 peak will last.
Where does off-grid power still fit?
Off-grid supply remains part of the near-term commercial pitch. MLQ.ai earlier covered Venture Global's pitch of 5 GW of off-grid power for AI data centers, showing that dedicated generation still attracts large proposals. That project-level marketing does not disprove Ito's long-term cost argument, because the reported comparison concerns how smaller plants operate relative to utility-scale generation.
Off-grid proposals can coexist with the current turbine cycle, even as Ito expects the cost balance to move toward utilities. Watch whether utilities and IPPs can add capacity quickly enough to serve grid-connected data centers, and whether off-grid developers can narrow the operating-cost gap.
mlq.ai (Source)