AI & Compute · 3 min read
Abbott's Office Reopens Queue for 1,800+ Data Center Projects
Texas resumed permit reviews for more than 1,800 stalled data center projects, reopening a queue tied to 474 GW of power requests ahead of January's policy shift.
Key takeaways
- More than 1,800 data-center projects were caught by Texas's August permit pause, which has now been lifted.
- The pause covered 474 GW of new power requests, a pipeline figure rather than confirmed operating capacity.
- Texas suspended 17 more construction permits and shut an automated portal in October; ERCOT's information gathering is complete.
- The Financial Times reported builders are racing for approvals before Democrat Gina Hinojosa's January arrival.
- New York's year-long ban applies above 50 MW; Amazon abandoned four Northern Virginia data-center plans after public outcry.

Texas has resumed approvals for more than 1,800 data-center projects that outgoing Republican Gov. Greg Abbott’s office put on hold in August, when a moratorium covered 474 gigawatts of new power requests.
The 474-GW number describes applications for power, not commissioned computing capacity. Abbott’s office did not disclose how many projects have cleared final review, what computing capacity they would support, or how much electricity ERCOT expects Texas to serve.
In October, Texas suspended 17 additional data-center construction permits and shut down an automated portal found to be issuing new approvals. The portal is expected to return because Abbott’s office confirmed that the Electric Reliability Council of Texas (ERCOT), which manages the state’s grid, has finished gathering information on data centers’ effects on local communities.
Why did Texas freeze the permit queue?
Abbott’s office tied the pause to grid strain and said its “top priority is to protect Texans’ safety and quality of life.” The stated concern centered on the amount of power new data centers would require from a grid also serving homes and other customers.
The Financial Times reported that builders are racing to secure approvals before Democrat Gina Hinojosa takes office in January and that Hinojosa has pledged to rein in new data-center construction, turning permit timing into a policy risk rather than a routine administrative delay.
What does restarting approvals change?
The stated condition for restarting reviews has been met: ERCOT has completed the requested information gathering. Neither the directive nor ERCOT’s findings supplied a processing schedule, and new power-request approvals are not expected to come quickly.
The queue reopened. The calendar did not.
For developers, two clocks now run at once: a political clock toward Hinojosa’s inauguration and a technical clock for power-service review. The 1,800-plus figure counts projects caught by the pause, not operating campuses; the 474-GW total covers requests, not contracted load.
No approval total or project list accompanied the directive, so the commercial effect remains uncertain. Builders that clear the queue before January could preserve their option to proceed under the current rules; those still waiting face the prospect of a stricter review policy.
Can data centers reduce their reliance on ERCOT?
According to the report, some developers are already pursuing their own power centers to reduce or eliminate reliance on the local grid. Texas’s large gas supply makes gas turbines a viable option, while what the report described as a lax regulatory environment makes that route easier to consider.
For operators, self-generation changes the trade-off: they can insulate some computing load from grid constraints, but they must secure fuel and dedicated generation instead. The Texas projects remained unnamed, and no figure quantified how much capacity their developers expect to operate outside ERCOT’s system.
Others are looking beyond conventional gas generation. In Mississippi, Elon Musk’s xAI installed eight converted jet engines to power its data center, a configuration the report said carried known health risks.
What could change in January?
The report said local opposition remains centered on environmental effects and higher electricity costs for residents. Those pressures give Hinojosa’s pledge to restrain new construction political force, although no specific permit rules or power-request thresholds for her administration have been set out.
Texas is not alone in reshaping the market for large computing projects. New York began enforcing a year-long ban earlier this year on data centers larger than 50 megawatts. In Northern Virginia, Amazon abandoned plans for four new data centers after public outcry, and the land will go to housing.
The immediate commercial contest therefore runs through permitting, grid access and dedicated power. Developers that obtain approvals and workable power arrangements before January may gain schedule certainty; slower reviews could push more reliance onto self-generated power and intensify local opposition over energy use and bills.
No forecast emerged for how much data-center capacity Texas will add, nor for retail electricity prices. If January arrives before the queue clears, developers with approvals and dedicated power will hold the stronger commercial position, while local opposition over bills will constrain how quickly new capacity arrives.