Core Scientific Files $1.3 Billion Data Center Plan at AMD-Leased Texas Campus
Core Scientific filed a $1.3 billion, 341,326-square-foot data center plan for Quinlan, Texas, where AMD will lease 110 MW of the campus's planned 285 MW capacity.
- By
- Grace Kim
- Filed
- Channel
- AI & Compute
- Read
- 3 min read
Core Scientific has filed plans for a $1.3 billion data center building in Quinlan, Texas, roughly 53 miles northeast of Dallas, on the Hunt County campus where AMD is set to lease 110 megawatts.
A subsidiary, Telios Quinlan One, LLC, registered the project with the Texas Department of Licensing and Regulation on Nov. 13 under the name "Core Scientific - Hunt." The filing lists an estimated cost of $1.3 billion. It describes a new 341,326-square-foot "data center core and shell building with site and infrastructure improvements" at 4852 County Road 3507.
The timeline is specific. Construction would run from Nov. 24, 2026 to Sept. 4, 2028. Gensler is the design firm. No tenant is named in the filing. Telios Quinlan One is the company Core Scientific bought to acquire the site, DCD reported.
What does the filing cover?
The permit covers one building. Core Scientific has said the Hunt County campus will hold several. The 341,326-square-foot structure is therefore the first documented phase of a larger buildout, not the full campus.
The land purchase closed on May 5 for about $232.5 million, according to Core Scientific's third-quarter 10-Q filing. The deal came with an electric service agreement expected to support about 430 MW of gross utility power. The company also holds an approved ERCOT interconnection ramp schedule for the site.
When Core Scientific announced the purchase in March, it said the campus could support up to 285 MW of leasable capacity across several buildings, start energizing in 2027 and reach full power by 2029, DCD reported.
How does the AMD lease fit?
In July, Core Scientific signed leases with AMD and an unnamed neocloud for about 530 MW of critical IT capacity across five of its sites. Each lease runs 15 years with three five-year options. The company also gave AMD a right to reserve another 1,925 MW through Dec. 28, 2028.
None of those leases had started as of Sept. 30, the 10-Q shows.
AMD is set to lease 110 MW in Hunt County, DCD reported. That figure equals just under 40% of the planned 285 MW of leasable capacity, by calculation. The remaining capacity at the campus has no publicly named tenant.
The lease structure signals how chipmakers are now securing power directly. AMD's July agreements with Core Scientific, combined with the 1,925 MW reservation right, lock in electrical capacity years ahead of demand rather than buying servers or buildings outright.
Why is Core Scientific building?
The company began as a bitcoin miner. It has been exiting mining to host AI computing. CoreWeave is its other major customer, alongside AMD and the unnamed neocloud.
The Hunt County filing is the concrete expression of that pivot. A $1.3 billion core-and-shell building, with construction stretching into 2028, is a multi-year capital commitment to hosting third-party compute rather than running its own mining rigs.
The company's disclosure timeline frames the scale. The July leases cover about 530 MW. The reservation right held by AMD covers almost four times that amount, at 1,925 MW, through the end of 2028.
What happens next?
Construction on the filed building cannot begin before Nov. 24, 2026. Completion is set for Sept. 4, 2028. That schedule aligns with the March statement that the campus would start energizing in 2027 and reach full power by 2029.
Two open questions shape the campus outlook. The filing names no tenant for the building, and AMD's 110 MW commitment accounts for under 40% of planned capacity, leaving roughly 175 MW at Hunt County without a disclosed customer. Whether AMD exercises part of its 1,925 MW reservation right, and whether the leases that had not started as of Sept. 30 commence on schedule, will determine how quickly the $1.3 billion commitment converts into revenue.
In a related transaction, AMD separately closed its $8.2 billion purchase of World Labs on Monday.
Source: mlq.ai
More from Grace Kim
Show full bio
Market editor covering people, launches and day-to-day practice in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.
1,035 articles
Related articles
coreweave-pleads-with-texas-governor-elect-let-permitted-data-centers-finish
CoreWeave Pleads With Texas Governor-Elect: Let Permitted Data Centers Finish
spacexs-24b-starbase-power-compute-plan-faces-hearing
SpaceX’s $24B Starbase Power, Compute Plan Faces Hearing
integra-s-8-billion-quanah-data-center-filing-raises-cost-questions
Integra's $8 Billion Quanah Data Center Filing Raises Cost Questions
tsmc-weighs-a-second-fabrication-site-in-texas-08d7f01d