ERCOT's Batch Zero Audit Hits December Deadline With a New Governor Waiting
ERCOT files its Batch Zero audit by Dec. 10 covering 194 GW of conditionally classified load — but restart decisions now rest with governor-elect Gina Hinojosa after Jan. 19.
- By
- Rebecca Stone
- Filed
- Channel
- AI & Compute
- Read
- 4 min read
By Dec. 10, ERCOT must file its Batch Zero eligibility verification report and community impact review with the Public Utility Commission of Texas — and even projects that pass will stay frozen, because the audit does not restart energization approvals or lift the state's permit freeze. The PUCT meets Dec. 17, likely its last session under Gov. Greg Abbott's appointees, Latitude Media reported Nov. 16. Both decisions about what happens next now fall to governor-elect Gina Hinojosa after Jan. 19.
The numbers at stake are enormous. On Sept. 3, ERCOT provisionally placed 204 projects totaling 66.4 GW in Batch Zero's base tier and 158 projects totaling 127.9 GW in the studied tier. It excluded 373 projects with 302.2 GW. All told, Abbott's Aug. 3 directive cited roughly 474 GW of pending interconnection requests to the ERCOT grid — about 90% from data centers, per Utility Dive — more than five times ERCOT's record peak demand.
What is Batch Zero?
ERCOT's first attempt to study large loads as a group rather than one request at a time. Approved in June 2026 through planning guide rule change PGRR 145, it sorts projects of 75 MW or more into tiers: base load enters ERCOT's starting study model, studied load qualifies but still faces evaluation and capacity allocation, and excluded projects wait for a future interconnection process.
Publicly traded developers disclosed their September results. Galaxy reported about 4.2 GW across five Texas projects, including 1.63 GW of base load at Helios. IREN reported 2 GW of conditional base load at Sweetwater. CleanSpark reported 585 MW of base load and 300 MW of studied load. Cipher received conditional classifications covering 3.2 GW.
How the freeze took hold
Abbott's Aug. 3 letter directed the PUCT and ERCOT to audit data centers in the interconnection queue and deny grid connections to any that fail. ERCOT paused energization approvals for large data centers and crypto facilities. The audit asks whether each project pays its own way, brings its own power, supplies or reuses its water, limits neighborhood effects, and who owns and controls it.
On Sept. 21, Abbott told the Texas Commission on Environmental Quality to stop processing data center permits until ERCOT and Texas Water Development Board audits finish. "Until they do, TCEQ will issue no permits sought by data center projects," he wrote.
The freeze caught projects that were furthest along. ERCOT said in August that 17 large loads, mostly data centers, had completed stability studies and expected to come online this year — about 6.6 GW of combined peak demand ramping over roughly five years. None had energization approval. The community impact review also reaches data centers and crypto facilities of 25 MW and above; ERCOT counted about 157 medium-sized facilities totaling almost 8,800 MW in an April snapshot.
The study itself is slipping. "We will not have the study done by April 9, 2027," ERCOT general counsel Chad Seely told the commission in August. ERCOT has not proposed a new date.
What does Hinojosa change?
Hinojosa, a Democrat who takes office Jan. 19, 2027, said in an Oct. 22 video she would issue a moratorium on all data center approvals until the Legislature passes protections, the Texas Tribune reported. Abbott froze the queue through letters to the PUCT, ERCOT and TCEQ — his successor can use the same tool, Latitude Media noted, though changing Senate Bill 6, which rewrote how large loads connect to the grid, needs the Legislature.
Lawmakers have already filed bills to repeal the industry's sales tax exemption and require PUC permits. Developers are lobbying: CoreWeave CEO Michael Intrator wrote to Hinojosa's team asking for the "responsible completion of permitted projects." Jefferies analysts, in a post-election note, said they doubt Hinojosa reverses Abbott's changes and called a legislative compromise that codifies consumer protections the most plausible outcome. "The pause could be long," they wrote.
Who is exposed?
Skybox Datacenters and its subsidiary Texas Data Center Campus Power filed an Oct. 23 complaint against ERCOT at the PUC, challenging the reclassification of project BZ-465 out of base load (Docket 60431). Mesquite H2 filed a separate complaint over project BZ-17 (Docket 60410). No ruling had appeared in either docket as of Nov. 16.
Power producers are exposed too. Jefferies says ERCOT forward wholesale prices already assume about 6 GW a year of new grid-connected data centers; slower arrivals would push prices down, helping consumers and hurting plant owners. NRG Energy and Vistra shares each fell 14% after the election. Texas holds about 23% of planned U.S. data center capacity, per MLQ.ai's tracker.
Some projects sit outside the freeze. Self-powered sites, projects already approved and under construction, and facilities outside ERCOT's footprint aren't covered, per mgrid's summary. Developers kept filing anyway: Integra's $8 billion building in Quanah, Core Scientific's $1.3 billion site near Dallas, and more than $24 billion planned by SpaceX at Starbase.
Whether the Dec. 17 PUCT meeting produces final classifications or another holding pattern, the real decision on when Texas restarts its data center queue now rests with a governor who has promised not to restart it at all.
Source: mlq.ai
More from Rebecca Stone
Show full bio
Correspondent covering technology and product news in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.
1,039 articles
Related articles
300-plus-data-center-bans-have-delayed-only-three-us-projects-1ef8014b
300-Plus Data Center Bans Have Delayed Only Three US Projects
vistra-down-32-as-texas-data-center-approvals-stall
Vistra Down 32% as Texas Data Center Approvals Stall
texas-moratorium-threat-meets-coreweave-s-46-9-billion-debt-wall
Texas Moratorium Threat Meets CoreWeave's $46.9 Billion Debt Wall
coreweave-s-13-billion-guide-sends-bloom-energy-up-15-percent
CoreWeave's $13 Billion Guide Sends Bloom Energy Up 15 Percent