Google seeks 1.2 GW grid link for second Châteauroux-area site

Tricolore Computing requested a 1.2 GW grid connection in Indre. RTE proposes €67 million of work, but Google says Ozans and other sites remain exploratory.

By Tom Whitfield611 words

Key takeaways

  1. Tricolore Computing requested a 1.2 GW connection in Villedieu-sur-Indre.
  2. RTE proposed €67 million of grid work with a seven-to-eight-year completion schedule.
  3. Ozans covers about 195 hectares and is estimated at $10 billion and about 1.2 GW.
  4. Google targets a 120 MW first building for construction in 2028 and commissioning in 2030.
  5. The Ozans public consultation opened Nov. 2 and ends Jan. 10, 2027.
Google seeks grid connection for a second 1.2 GW data center site near Châteauroux, France
Google seeks grid connection for a second 1.2 GW data center site near Châteauroux, France — Didier VEILLON / unsplash

Google subsidiary Tricolore Computing requested a 1.2 GW grid connection for a proposed data center in Villedieu-sur-Indre in central France, Mediapart and Lighthouse Reports said on Nov. 23.

French grid operator RTE proposed a €67 million connection that could take seven to eight years to complete, Datacenter Dynamics reported Nov. 25, citing Mediapart. The request concerns a second Google site in the Châteauroux area, alongside Ozans, which is already in public consultation. Google says it has made no final decision on either project.

What has Google actually requested?

Tricolore's filing asks RTE to assess a 1.2 GW connection at Villedieu-sur-Indre, in the Indre department. RTE's €67 million proposal covers the grid connection and could take seven to eight years to complete. The filing identifies a grid option rather than a final construction commitment.

A Google spokesperson told DCD:

“No final decision has been made on Ozans, or any other site, which are strictly part of ongoing, exploratory long-term planning rather than active parallel projects.”

The spokesperson said the company continuously explores land and grid opportunities. Against that wording, the filing expands Google's site options without proving that two simultaneous 1.2 GW campuses will proceed.

What does the mayor know about Villedieu?

Mediapart reported that Villedieu-sur-Indre Mayor Xavier Elbaz had not received notice of the filing. DCD reported that Elbaz had spoken with Google, which told him the plans were on hold while the company focused on Ozans.

He also said the current landowner opposed selling the site to Google. Separately, Mediapart reported that Google had approached several municipalities in Indre during recent months to find a “mirror data center” to Ozans.

The accounts differ in emphasis: Google describes exploratory land and grid searches, while the mayor describes a paused plan and a landowner objection. Villedieu therefore remains an option on paper, not a secured site.

What is already advanced at Ozans?

The Ozans site, in the commune of Étrechet southeast of Châteauroux, covers about 195 hectares that Châteauroux Métropole agreed to sell to Tricolore. Google estimates the development at $10 billion and about 1.2 GW in its most developed form.

The plan calls for six to eight buildings in phases. Google hopes to start the first 120 MW building in 2028 and commission it in 2030. These are Google's estimates and targets, not operating capacity.

Formal public consultation under the Commission nationale du débat public, run jointly with RTE's connection project, opened on Nov. 2 and runs until Jan. 10, 2027. Engie signed a memorandum of understanding with Google this month on energy supply for the development.

Ozans has moved beyond site selection, but its first building remains a 2030 commissioning target.

How does Google use French data centers now?

Google has no self-built data centers in France. It relies on third-party facilities from Equinix, Digital Realty and Global Switch, according to DCD. The Ozans and Villedieu proposals would mark a change from that arrangement, but neither project has reached operation.

The separate 1.2 GW figures should not be treated as confirmed French capacity. Ozans represents the more developed plan, while Villedieu remains a connection request with a seven-to-eight-year grid schedule.

RTE's €67 million figure covers only the proposed grid connection; it does not establish the total investment required for either site. The next checkpoints are RTE's work on the Villedieu connection, the Ozans public consultation ending Jan. 10, 2027, and the planned 2028 construction start. Those milestones will show whether Google's French expansion becomes operating capacity or remains a long-term option.

mlq.ai (Source)

Filed under

Share this article:

More from Tom Whitfield

Tom Whitfield

Show full bio

Staff writer covering companies, deals and strategy in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,282 articles

Read also

« Previous articleNext article »