AI & Compute · 4 min read
GS breaks ground on 2.4-GW AI data center in South Korea
GS Group broke ground on a planned 2.4-GW AI data center in Donghae; its permitted first 100 MW targets early 2028, while larger phase schedules extend through 2030.
Key takeaways
- GS broke ground on a planned 2.4-GW AI data center in Donghae on Saturday, Nov. 28.
- The first 100 MW has building and power permits, active construction and a first-half 2028 completion target.
- GS put planned investment at 30 trillion won; Nocut News estimated up to about 120 trillion won including GPUs and memory.
- Schedules for the two 1.2-GW phases differ: 2028-2029 in the June plan, or 2029-2030 after the ceremony.
- Rules effective March 2027 provide one-stop permitting and a below-50-MW power-grid assessment exemption outside the capital region.

GS Group broke ground on Saturday, Nov. 28, on a planned 2.4-GW AI data center in Donghae, Gangwon Province, where the company targets completion of the first 100 MW in the first half of 2028.
The campus at the Bukpyeong 2 General Industrial Complex forms one of three megaprojects the South Korean government announced in June. South Korean President Lee Jae Myung attended the ceremony, according to his office. About 270 people attended, including GS Group Chairman Huh Tae-soo and Deputy Prime Minister and Science and ICT Minister Bae Kyung-hoon.
What does the government expect from the campus?
At the ceremony, Lee said: “The whole world is waging a war without gunfire over AI technological superiority.” He added that the data center “will serve as Asia's largest AI infrastructure and as seed money that draws preemptive investment from global companies,” Seoul Economic Daily reported. His office described it as Asia's largest AI infrastructure facility.
The statements put the project at the center of the government's AI infrastructure strategy. They do not answer who will use it, which GPUs it will contain or how it will obtain power. Public backing is clear, while execution still depends on private commitments.
What will it cost, and when will it open?
GS announced the project on June 29 at a government briefing on the three megaprojects, putting planned investment at 30 trillion won for the full 2.4 GW, Seoul Economic Daily reported. Nocut News said the total could reach about 120 trillion won once GPU and memory costs are included.
The first figure represents GS's announced plan. The second is a broader media estimate rather than a disclosed purchasing schedule.
The schedule differs by outlet:
- First 100 MW: Building and power permits are in place, construction is under way, and GS targets completion in the first half of 2028. Donghae granted the building permit in October.
- First 1.2-GW phase: Seoul Economic Daily reported a 2029 date after the ceremony; the June plan and Nocut News gave 2028.
- Second 1.2-GW phase: Seoul Economic Daily reported 2030; the June plan and Nocut News gave 2029.
The first 100 MW has a permit-backed target. The two larger phases remain roadmap dates because the cited reports assign different years.
What remains uncommitted?
GS has not named tenants, GPU suppliers or the campus power source in the cited reports. The disclosed 2.4-GW figure therefore describes planned infrastructure scale, not a disclosed GPU configuration or contracted customer base.
In June, GS said GS Power, GS EPS and GS E&R have experience supplying large amounts of power. That group experience does not commit any of them to the Donghae site.
The 120 trillion won estimate adds GPUs and memory to the announced figure, and the cited reports disclose no supplier, product family or purchasing terms. The first construction package therefore has permits, but customers, GPUs and power remain uncommitted.
How can policy speed the build?
Reports said Gangwon State, Donghae and GS signed a business agreement on July 6 and completed key permits within about three months. Gangwon has proposed designating the province a special zone for AI data centers. That status remains a proposal rather than an approved designation.
Subordinate rules under Korea's Special Act on the Promotion of the AIDC Industry went out for legislative notice on Nov. 20 and take effect in March 2027, Digital Today reported. They include one-stop permitting and exempt AI data centers outside the capital region from power-grid impact assessments when capacity falls below 50 MW.
The initial 100-MW portion sits above that threshold, so the exemption does not cover GS's first tranche. Lee's visit to SK Group's AI data center construction site in Ulsan the previous week, reported by The Korea Herald, placed the GS project within the same domestic policy push.
The rule change can simplify approvals, but GS still needs project-level tenant, equipment and power commitments. National support does not remove those commercial requirements.
What will determine the commercial result?
GS's immediate test is delivery of the permitted 100 MW in the first half of 2028. Its larger schedule depends on resolving whether the two 1.2-GW phases arrive in 2028-2029 or 2029-2030, while GPU and memory prices will test the gap between the two investment estimates.
With the new rules taking effect in March 2027, GS's ability to secure tenants, GPUs and power will determine whether its 2.4-GW plan gains traction alongside SK's Ulsan project. The next hard measure will be completion of the first 100 MW on schedule.