JERA, Japan's largest power generator, is negotiating with Anthropic and Meta to place behind-the-meter data centers beside its Tokyo-area plants, following a $15 billion, 400 MW Dell-backed deal at Chiba.
Key takeaways
- JERA's chief told Nikkei Asia on Nov. 27 that the company is in talks with Anthropic, Meta and other US tech firms on behind-the-meter data centers near Tokyo.
- On Oct. 1, JERA signed a memorandum with Dell and RHAELM for a 400 MW-class AI data center at Chiba, costed at $15 billion, phased from 2028.
- JERA is to supply land and up to 400 MW of power for 15 to 25 years at Chiba; full capacity is targeted for 2029.
- JERA and RHAELM plan to screen JERA's 26 Japanese thermal plants for sites, targeting several gigawatts of AI capacity in the 2030s.
- No megawatts, investment figure, schedule or company statements accompany the reported Anthropic and Meta talks.

Japan's largest power generator is negotiating with Anthropic, Meta and other US technology companies to build data centers beside its power plants around Tokyo. JERA's chief disclosed the talks to Nikkei Asia in a report published early on Friday, Nov. 27. The discussions concern "behind the meter" sites, where a data center sits next to a plant and draws electricity directly rather than through the transmission grid.
Nikkei described negotiations, not a signed contract. The report gives no site count, megawatt figure, investment amount or start date. It does not say how far the talks with each company have advanced. Anthropic, Meta and JERA had issued no statements when this article went to press, and subsequent coverage has repeated the Nikkei account without adding detail. Some relaying posts named Amazon, Microsoft and Google as well; that could not be confirmed in Nikkei's text.
Where would the capacity sit?
Nikkei illustrated the report with JERA's Chiba Thermal Power Station on Tokyo Bay, identified as a planned data center site. That project is already documented. On Oct. 1, JERA, Dell Technologies and UK-based developer RHAELM signed a memorandum of understanding for a 400-megawatt-class AI data center on land beside the Chiba plant.
The division of labor is set. RHAELM develops, builds, operates and finances the facility. Dell supplies rack-scale AI systems. JERA provides the land and up to 400 MW of power for 15 to 25 years. Apollo Global Management is expected to act as RHAELM's investment and financing partner.
The companies put the project's cost at $15 billion. Phased operation is targeted to begin in 2028, with full capacity reached in 2029. JERA and RHAELM also plan to screen JERA's 26 thermal power plants across Japan for additional sites, aiming at several gigawatts of AI data center capacity nationwide in the 2030s. The Nikkei report does not say whether Anthropic or Meta would be tenants at Chiba or at other JERA plants.
Why is a power producer courting AI labs?
JERA is owned jointly by Tokyo Electric Power and Chubu Electric Power. Building inside or beside a plant lets a data center skip the queue for new high-voltage transmission, a constraint that has slowed AI projects in grid-constrained markets. At the October signing, JERA Global CEO Yukio Kani said the company's LNG value chain, from fuel procurement through generation, can give AI infrastructure "access to the large-scale, reliable energy it needs."
The Anthropic and Meta talks are not JERA's first move in this direction. The company has lined up data center partners for more than a year. In June 2025 it signed a basic agreement with Sakura Internet to study a data center on the grounds of one of its LNG-fired plants, including a Tokyo Bay site, with a plan to use cold energy from LNG for equipment cooling.
What remains unconfirmed?
Three things are established on paper: the Chiba memorandum with Dell and RHAELM, the June 2025 Sakura Internet study agreement, and the gigawatt-scale site screening across 26 plants. The Anthropic and Meta negotiations rest on a single Nikkei interview with JERA's chief, with no capacity, schedule or tenant commitment attached.
The commercial logic points one way. A 400 MW campus at $15 billion, with a 15-to-25-year power contract, gives JERA a template that Anthropic and Meta could replicate across other Tokyo-area plants if the talks mature. Expect the next hard numbers — megawatts, dollars, tenants — to surface when any agreement moves from interview to announcement.