Kumyang Green Power Wins 230 Billion Won AI Data Center Contract
Kumyang Green Power signed a 230 billion won contract with Mega Data Korea for the Wonju Mega Cluster AI data center, equal to 86.87% of its 2025 revenue. Shares closed up 30% at 9,620 won.
Key takeaways
- Kumyang Green Power signed a 230 billion won contract (excluding VAT) with Mega Data Korea, filed Nov. 20
- The award equals 86.87% of the company's 2025 consolidated revenue of 264.8 billion won
- A 20% advance of 46 billion won is payable only after the developer's project financing is approved
- Construction started Nov. 20 and runs to completion on March 30, 2029
- Shares closed up 30.00%, the daily limit, at 9,620 won on Nov. 23
Kumyang Green Power has signed a 230 billion won contract, excluding VAT, for the electrical and telecommunications work at the Wonju Mega Cluster AI data center. The deal equals 86.87% of the South Korean contractor's 2025 consolidated revenue of 264.8 billion won, according to its regulatory filing of Nov. 20.
The client is Mega Data Korea. The filing states the two companies have not worked together on a similar contract in the past three years. That absence matters for a single award of this scale, and the filing offers no comfort beyond the contract terms themselves.
Kumyang Green Power builds electrical systems for power plants and industrial sites. The Wonju award, in Gangwon Province, moves the company into the build-out of AI data center infrastructure, the segment now pulling in Korean construction and electrical firms.
What are the payment terms?
The payment structure is conventional but conditional. The filing sets out three stages:
- 20% advance, or 46 billion won
- 75% in monthly progress payments
- 5% after completion
The advance carries a caveat. The filing says the developer will pay it only after the project financing for the scheme is approved. Until that approval lands, the contractor has a signed contract but no cash.
How long does the work run?
Construction started on Nov. 20, the same day as the filing. The contract runs to completion on March 30, 2029, a schedule of roughly three and a half years for electrical and telecom installation. The filing also warns the contract value may change once detailed design is finalized and design changes are priced in.
Neither the filing nor Korean press reports gave the data center's planned capacity, so the IT load behind the contract remains unknown. A 230 billion won electrical scope implies a large facility, but implication is not a figure.
How did the market respond?
Shares closed up 30.00% on Nov. 23, the daily limit, at 9,620 won. The move prices in full execution of the award. The filing's own conditions, financing approval and possible design-driven value changes, argue for restraint.
The company's revenue base adds context. A contractor with 264.8 billion won in 2025 consolidated revenue has now taken on a single project worth almost nine-tenths of that figure, concentrated in one client it has not served in three years. Concentration cuts both ways when monthly progress payments depend on one developer's financing closing.
The Wonju Mega Cluster contract runs to March 30, 2029, and its final value will hinge on the detailed design and the approval of the project financing that triggers the 46 billion won advance.