Nebius adds 134 MW in third Mega Or data center deal

Nebius agreed to lease 134 MW from Mega Or at Beit Shemesh and Masmiya, pushing contracted capacity to 222 MW, while a frozen grid application leaves Q2 2028 delivery conditional.

By Rebecca Stone556 words

Key takeaways

  1. Nebius agreed to lease 134 MW of IT capacity at Beit Shemesh and Masmiya.
  2. The seven-year lease includes a five-year extension option on the same terms.
  3. Mega Or estimates $1.6 billion in construction costs and about NIS 550 million in annual net operating income once fully occupied.
  4. Both facilities are due by the end of Q2 2028, but Masmiya’s grid application is frozen.
  5. The agreement brings Nebius’s contracted capacity with Mega Or to 222 MW.
Nebius adds 134 MW in Israel in a third data center lease with Mega Or
Nebius adds 134 MW in Israel in a third data center lease with Mega Or — wal_172619 / pixabay

By Rebecca Stone

Nebius has agreed to lease 134 MW of IT capacity from Tel Aviv-listed developer Mega Or at two Israeli data center sites, lifting the Amsterdam-based AI cloud provider’s contracted capacity with Mega Or to 222 MW.

Calcalist reported the agreement on Thursday, Nov. 19. The 134 MW sits in phase two of Mega Or’s Beit Shemesh campus, which is under construction, and at a planned site in Masmiya. The lease runs seven years from delivery, with an option for Nebius to extend it for five more years on the same terms.

What does the lease mean for Mega Or?

Mega Or, through its Mega DC unit, expects the agreement to generate average annual net operating income of about NIS 550 million, roughly $170 million, once both facilities are fully occupied. That is a developer forecast tied to occupancy, not booked cloud revenue.

It estimates construction costs of about $1.6 billion, or $12 million per megawatt of IT capacity. Both facilities are due for completion by the end of the second quarter of 2028. The cost, income and schedule figures are forward-looking estimates, not delivered results.

What can block Masmiya?

Masmiya appears in Mega Or’s latest quarterly report as land earmarked for future development. The site has no grid connection. The grid is the gate.

Calcalist reported that processing of the application “is currently frozen by the Electricity Authority.” The report also states: “Securing that approval is a prerequisite for finalizing the transaction with Nebius.” That condition makes the grid application a gating issue for the planned Masmiya capacity, even though phase two of Beit Shemesh is already under construction.

The end-Q2 2028 target therefore spans two different positions: Beit Shemesh in construction, Masmiya awaiting electricity approval. Without a grid link at Masmiya, both sites cannot meet the stated completion schedule.

How does this fit Nebius’s build-out?

This is the third agreement between the companies. Nebius took 8 MW at Mega DC’s Modi’in data center in May 2025, then 80 MW at Beit Shemesh and Masmiya in January 2026. Including the new lease, Calcalist said Nebius’s contracted capacity with Mega Or reaches 222 MW.

Nebius could take possession of the 58 MW first phase at Beit Shemesh as early as this quarter. That staged handover gives the cloud provider an earlier capacity foothold while the new 134-MW agreement remains tied to phase two and Masmiya.

The lease adds to a capacity build-out that has weighed on Nebius shares, Calcalist said. On Nov. 12, the company raised its 2026 capital spending plan to about $27 billion and guided revenue to the low end of its range, citing colocation delays.

That combination makes timing commercially material: Nebius has raised capital spending while naming colocation delays as the reason for low-end revenue guidance. Mega Or’s NIS 550 million operating-income projection likewise depends on full occupancy, not merely a 222 MW contract position.

Until Masmiya secures grid approval, the 134-MW transaction cannot be finalized and the Q2 2028 completion schedule remains conditional. Once approval clears, the project would give Nebius a path to 222 MW of contracted Israeli capacity and move Mega Or’s projected $1.6 billion build toward the full-occupancy case behind its annual-income target.

mlq.ai (Source)

Filed under

Share this article:

More from Rebecca Stone

Rebecca Stone

Show full bio

Correspondent covering technology and product news in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,245 articles

Read also

« Previous article