North Carolina Orders 15-Year Contracts for 100 MW-Plus Data Centers
NCUC orders require 100 MW-plus data centers to sign 15-year Duke Energy contracts with 75% minimum bills, while approving $834 million in two-year rate increases.
- By
- Sophie Lindqvist
- Filed
- Channel
- AI & Compute
- Read
- 4 min read
North Carolina regulators now require data centers above 100 megawatts to sign 15-year power contracts and pay for at least 75% of their contracted demand whether or not they use the electricity. Orders issued Monday, Nov. 16 by the North Carolina Utilities Commission (NCUC) create a new "DC Schedule" for Duke Energy's largest customers, according to an 8-K Duke filed at 6:01 a.m. ET on Tuesday.
The same orders approved the rate-case settlements of Duke Energy Carolinas and Duke Energy Progress without modification. Duke Energy Carolinas gets $496 million over two years, a 7.4% net increase, down from $1,002 million requested. Duke Energy Progress gets $338 million, or 6.8%, down from $729 million. Both utilities received a 9.8% return on equity on a 53% equity share.
Duke said it is "still assessing" the data center portion. It will keep engaging with customers and stakeholders on implementation.
What does the DC Schedule require?
Duke's fact sheets list terms, some carried over from the Oct. 6 large-load settlement and some new:
- Minimum contract terms of 15 years for data centers above 100 MW.
- Minimum billing demand of 75% of contract demand.
- Interim curtailment provisions.
- Upfront customer payment, as contribution in aid of construction, for dedicated facilities.
- A letter of credit for all transmission network upgrades, with partial direct assignment of costs based on customer benefit under a method still to be set.
- Liquidated damages for early termination.
- A stranded-generation charge, with security posted and an extra payment at contract end, also under a method still to be set.
Two mechanisms lack defined methods. That gap matters. The transmission and stranded-generation terms respond to the central complaint about the October deal: under that settlement, transmission upgrades other than dedicated facilities would initially have been spread across all customers and repaid over a data center's contract, as WUNC reported. The Southern Environmental Law Center said the deal did not guarantee data centers would pay the full cost of those upgrades.
The settlement also exempted companies signing with Duke on or before June 1, 2026. Duke's filing does not say whether the commission's schedule keeps that exemption. The filing also does not describe the schedule as a new customer class, though Attorney General Jeff Jackson asked the commission in September to create one.
How much did the rate settlements cut?
Both utilities filed in November 2025 for two-year increases under North Carolina's performance-based regulation, with multi-year rate plans for capital projects. The commission approved 9.8% ROE against 10.48% requested in rebuttal and 10.95% in the original filings. That is below the 10.1% allowed Duke Energy Carolinas in its last case; Duke Energy Progress stays at 9.8%.
| Item | Duke Energy Carolinas | Duke Energy Progress |
|---|---|---|
| Allowed ROE | 9.8% | 9.8% |
| ROE asked (rebuttal) | 10.48% | 10.48% |
| Prior allowed ROE | 10.1% | 9.8% |
| NC retail rate base | $25.7B | $17.8B |
| MYRP capital | $3.8B | $3.4B |
| Settled increase, 2 years | $496M | $338M |
| Net rate increase, 2 years | 7.4% | 6.8% |
Duke Energy Carolinas' settlement averages 3.7% a year, down from 15% in the original filing and 9.3% in its June rebuttal. Duke Energy Progress averages 3.4% a year, down from 15.1%. Part of Progress's reduction comes from stretching coal ash cost recovery from five years to eight and returning $120 million a year of production tax credits to customers in 2027 and 2028, up from $40 million in its request.
When do the new rates take effect?
The orders direct each utility to finalize the revenue requirement with the Public Staff, so the dollar figures remain provisional. Duke expects Year 1 rates to take effect on Jan. 1, 2027. Each utility will contribute $10 million of shareholder money for bill help and home repairs, and each expects a one-time $10 million pre-tax charge in the fourth quarter, which Duke will exclude from adjusted earnings.
The utilities will consider not filing another base rate case before Nov. 1, 2028, if allowed to defer costs of the approved Person County CC1 and Marshall combustion turbine projects.
Why does this matter beyond North Carolina?
Duke is one of many utilities fielding large requests from data center developers, and the question of who bears the risk increasingly lands before regulators across the US. Minimum terms, minimum bills and exit charges exist to keep residential customers from paying for plants and lines built for data centers that later shrink or leave. Duke narrowed its 2026 profit outlook with third-quarter results on Nov. 7. Whether the new contract terms actually insulate other customers will depend on the assignment and stranded-cost methods the commission has yet to define.
Source: mlq.ai
More from Sophie Lindqvist
Show full bio
News editor covering money, funding and market shifts around Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.
1,077 articles
Related articles
tva-books-1-7-billion-data-center-capacity-deal-at-1-5-million-per-mw
TVA Books $1.7 Billion Data Center Capacity Deal at $1.5 Million per MW
senate-bill-nears-vote-with-35-billion-data-center-grid-cost
Senate bill nears vote with $35 billion data-center grid cost
senate-clears-73-25-hurdle-for-data-center-power-bill
Senate Clears 73-25 Hurdle for Data Center Power Bill
ppl-lifts-capital-plan-to-25-billion-as-data-center-load-requests-hit-50-gw
PPL lifts capital plan to $25 billion as data center load requests hit 50 GW