Northwood Space links GEO satellite with 10 phased arrays in 7 days
Northwood Space built a Ventura ground site in seven days and held a full-duplex link with a U.S. government GEO satellite, using ten Portal arrays to receive and one to transmit.
Key takeaways
- Sept. 17: roughly one-hour full-duplex link with a U.S. government GEO satellite, with ten Portal arrays receiving and one transmitting.
- Site built in seven days — first arrays shipped Sept. 10 from Torrance, all ten online Sept. 11, first downlink Sept. 12, configured in the Space Force scheduling system Sept. 15.
- Ninth and last milestone of a nine-month prototype contract with Space Systems Command's BMC3I portfolio acquisition executive.
- $375 million Series C on Nov. 2, co-led by Andreessen Horowitz and DFJ Growth; 185,000-square-foot Torrance HQ and factory; $49.8 million Satellite Control Network capacity award in January alongside a $100 million Series B.
- Space Force estimates national security satellite contact demand could rise as much as 400%, according to Northwood.
Seven days after the first Portal phased-array antenna rolled out of Northwood Space's Torrance factory on Sept. 10, ten of those panels were holding a full-duplex link with a U.S. government satellite in geosynchronous orbit. The contact came Sept. 17 at a site Northwood assembled in Ventura, California, and lasted about an hour.
Ten arrays received. One transmitted. "Northwood, we have good data," the Space Force operations team told the company once the link was up, according to Northwood. The company disclosed the milestone in a blog post on Nov. 24.
Why ten arrays instead of one dish?
A GEO downlink arrives about ten billion billion times weaker than when it left the satellite, Northwood said, which is why such contacts have relied on large parabolic dishes with 20- to 40-foot reflectors.
Northwood instead combined ten Portal arrays into one larger receive aperture and used a single Portal array to transmit. In its Nov. 2 funding announcement the company said ten Portal arrays matched the receive performance of a 20-foot dish — a company claim, not an independently verified measurement.
How the seven days went
Northwood's own timeline reads like a checklist:
- Sept. 3 — a planned test at a site on another continent falls through.
- Sept. 10 — the first arrays leave the Torrance factory.
- Sept. 11 — all ten arrays online.
- Sept. 12 — first downlink.
- Sept. 12–14 — calibration on the sun and on passes of the JASON-3 ocean satellite, running through Sept. 14.
- Sept. 15 — the site is configured in the Space Force scheduling system.
- Sept. 17 — full-duplex GEO contact, roughly an hour.
Beamforming and pointing are set in software, Northwood said, which let the team adjust live when terrestrial interference disrupted tracking. No dish to re-aim. Just code.
What does completing the prototype change?
The contact was the ninth and last milestone of a nine-month prototype contract with Space Systems Command's Portfolio Acquisition Executive for Battle Management Command, Control, Communications and Space Intelligence, or BMC3I. Northwood had earlier shown full-duplex links with low Earth orbit satellites.
The pass was booked through the Joint Antenna Marketplace (JAM), the Space Force's system for buying commercial ground capacity. Via Satellite reported that the September demonstration was the first time JAM was used by operators of a commercial phased array.
That distinction matters commercially. Northwood's arrays are sold as commercial ground capacity, and JAM is the channel the Space Force uses to buy it, so a phased-array operator can bid for passes without the government owning a fleet of reflectors.
According to Via Satellite, completing the final prototype milestone means the Space Force can negotiate production agreements with Northwood without a new Federal Acquisition Regulation-based contract. Northwood said the Space Force estimates national security satellite contact demand could rise as much as 400%.
The software-defined pointing is the other differentiator. A 20- to 40-foot parabolic dish has to be physically aimed and repositioned by hand; Northwood's beamforming and pointing are set in software, which is why the team could retune tracking mid-pass when terrestrial interference broke through.
Who is paying for scale
Northwood raised a $375 million Series C on Nov. 2, co-led by Andreessen Horowitz and DFJ Growth, and runs a 185,000-square-foot headquarters and factory in Torrance. In January it won a $49.8 million Space Force award to add capacity to the Satellite Control Network, alongside a $100 million Series B.
The hardware question now has an answer. The open one is whether the Space Force converts a prototype into production orders under JAM without a new FAR contract, and whether Northwood can turn $375 million and a 20-foot dish's worth of claimed receive performance into scheduled capacity fast enough to meet a demand estimate running to 400%.
mlq.ai (Source)
More from Rebecca Stone
Show full bio
Correspondent covering technology and product news in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.
1,332 articles