Norway, Australia and Texas hit the brakes on data center grid deals
Statnett froze data center grid reservations through 2027 as requests hit 31,300 MW against a 25,000 MW peak, while NextDC cut FY27 EBITDA guidance to A$245-265 million.
- By
- Grace Kim
- Filed
- Channel
- AI & Compute
- Read
- 6 min read
Norway's Statnett will stop reserving grid capacity for new data centers until Aug. 1, 2027 at the latest, with 31,300 MW of reserved, queued and requested data center load stacked against a national record peak of just over 25,000 MW. The halt, announced Monday, protects power system operation while the government builds a licensing regime. Connected data centers and approved facilities remain unaffected.
The Norwegian freeze landed on the same day NextDC, Australia's listed data center operator, confirmed a broad construction pause. It is part of a spreading pattern. Texas froze new data center grid connections in August, Denmark paused new connection agreements in March, and both Nordic governments and U.S. politicians are now deciding who gets grid access first.
Why did Statnett stop handing out reservations?
The numbers explain the decision. Norwegian data centers hold 800 MW connected and 4,200 MW reserved. Another 9,100 MW sits in the queue. Requests for a further 18,000 MW have been filed. The total exceeds the country's all-time peak demand.
Data centers consume just over 3 TWh a year, out of roughly 140 TWh of total Norwegian consumption, according to E24. Statnett group director for system operation and market Peer Olav Østli said the pause allows the operator to put measures and a framework in place. He said data centers combine large capacity volumes with technical characteristics that matter for safe and stable operation.
Digitalisation minister Torgeir Micaelsen said the government will start work on a licensing scheme aimed at controlled growth. Regulator NVE has warned continued growth could cause power deficits and higher electricity prices.
Denmark set the precedent
Energinet, Denmark's grid operator, paused all new connection agreements in March after about 60 GW of projects queued against peak demand of roughly 7 GW. The pause was designed to last three months while Energinet set ranking criteria for large energy users. Data centers have since moved to the back of the Danish queue, behind projects tied to the green transition, E24 reported.
Both Nordic countries had marketed cheap hydro and wind power to data center builders. Meta president Dina Powell McCormick said last week that "every hyperscaler is now thinking about 'Do we need to build outside the United States?'" after the U.S. midterms.
What happened to NextDC in Melbourne?
NextDC's pause began with a single power line. In September, network company Jemena suspended parts of a 66kV line augmentation feeding the M3 site in Melbourne, citing community opposition and a lack of council consent. Jemena does not expect to restart before February 2027. The next supply increase is now expected in FY28.
Chief executive Craig Scroggie said work on projects without customer contracts stays on hold while the company concentrates on M3. The work "can't restart until we clearly communicate that we've solved this problem," he told a UBS conference, Reuters reported. He called the delays "reflective of the global environment" around social licence and public feeling about AI.
The financial damage is concrete. On Oct. 21 NextDC cut FY27 net revenue guidance to A$475-500 million from A$615-640 million, and underlying EBITDA guidance to A$245-265 million from A$385-410 million, after removing affected M3 contracts. The delayed M3 capacity "remains under contract, subject to the customer's rights." The shares fell 42% after the downgrade.
NextDC has halted new development projects and land acquisitions, deferred uncontracted expansion, and said its board will consider selling development sites. It holds A$8.7 billion of liquidity at Sept. 30 with no debt maturing before December 2029. A decision on its M3 stages 6 and 7 permit application is not expected until 2027 because of Victoria's Nov. 28 state election. The board will announce the outcome of its capex review by the Nov. 20 annual meeting.
Rivals Goodman Group and Digital Realty completed the purchase of a 9.9% stake in NextDC worth A$715 million, about $492 million. They said they have no current takeover plans but reserved the right to make one. Sydney has lost other projects: Stockland dropped a data center from its Kogarah golf course redevelopment on Sunday.
How far does the Texas freeze reach?
Texas already has a freeze in place. Outgoing Governor Greg Abbott halted new data center connections to the state grid on Aug. 3 and ordered an audit of power demand, environmental effects and tax breaks, due in December. ERCOT is tracking more than 400 GW of data center projects seeking connection. Texas holds 44.4 GW, or 23.2%, of planned AI campus capacity in MLQ's tracker.
Governor-elect Gina Hinojosa, who takes office Jan. 19, has said she will "issue a moratorium — a ban — on all data center approvals" until the legislature passes protections. CoreWeave has already asked her to let permitted projects finish. In Washington, Representative-elect Will Lawrence, who flipped Michigan's 7th District on a federal moratorium pledge, says he will push one in Congress. New York already pauses discretionary state permits for new data centers under a July executive order.
What do the pauses do to capital and power bills?
A grid queue rations interconnection. Developers can buy land and order chips quickly, but a transmission upgrade takes years, as Jemena's line shows. Statnett and Energinet chose to stop and set rules rather than hand out reservations they might not honor.
Hyperscaler spending is still flowing. Meta expects 2026 capital spending of $135 billion to $145 billion. The pauses shift where that capital lands: toward sites with existing reservations, on-site power, and jurisdictions still offering grid access. Google's $17 billion Cheyenne campus will run mainly on a 702 MW fuel cell plant. Developers are also buying used gas turbines and converted jet engines because new units ordered today will not arrive until about 2030.
Who pays for the grid is part of the same fight. A bipartisan Senate permitting bill, planned for a floor vote around Nov. 9, would require data centers to pay the full cost of the grid upgrades needed to connect them. Abbott wants Texas data centers to pay for their own electrical infrastructure. NVE's warning on Norwegian prices makes the same link between data center load and household bills.
Local opposition continues alongside the grid pauses. A coalition of speedway fans and insect conservationists is trying to block Google's planned campus east of London, Wired reported Monday. Google bought the 128-acre former Arena Essex speedway ground in Thurrock for £47 million in 2023. Buglife says the plan would remove about 80% of habitat on the site; its petition passed 30,000 signatures by August. Britain's growth minister said Saturday that data centers will proceed as "essential infrastructure."
The dates ahead frame the year: Victoria votes Nov. 28, Texas reports its audit in December, Hinojosa takes office Jan. 19, Jemena's earliest restart is February 2027, and Norway's pause ends by Aug. 1, 2027, when the licensing scheme's terms will decide which of the 27,100 MW of queued and requested Norwegian load gets built.
Source: mlq.ai
More from Grace Kim
Show full bio
Market editor covering people, launches and day-to-day practice in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.
763 articles
Related articles
voters-restrict-data-centers-in-40-of-41-ballot-measures-as-ai-stocks-slide
Voters Restrict Data Centers in 40 of 41 Ballot Measures as AI Stocks Slide
riot-s-28-billion-texas-lease-rewrites-the-ai-data-center-map
Riot's $28 Billion Texas Lease Rewrites the AI Data Center Map
openai-signs-3-2-gw-georgia-power-deal-with-1-000-mw-demand-response
OpenAI signs 3.2 GW Georgia Power deal with 1,000 MW demand response
30-data-center-capacity-puts-nvidias-growth-at-risk
30% of 2028 Data-Center Capacity Puts NVIDIA’s Growth at Risk