Ohio Clears 800 MW Gas Plant to Serve Single EdgeConneX Data Center
The Ohio Power Siting Board approved PowerConneX's up to 800 MW Ashville Energy Center on Nov. 19 with 41 conditions. The behind-the-meter gas plant will serve only an adjacent EdgeConneX data center, targeting Q2 2027 operation.
Key takeaways
- The Ohio Power Siting Board approved the up to 800 MW Ashville Energy Center on Nov. 19, 2025-scale case 26-196-EL-BGN, with 41 conditions.
- The behind-the-meter plant will serve only the adjacent EdgeConneX data center campus and will not connect to the public grid.
- PowerConneX filed on May 12, 2026; site prep was slated for Q3 2026 and commercial operation as early as Q2 2027.
- More than 80% of Ashville voters repealed the village's development agreement with EdgeConneX in a November referendum.
- The same meeting approved the 1,350 MW Fairfield Energy Center with 1,040 MW of battery storage on 122 acres, under 36 conditions.

Ohio regulators have approved an up to 800 MW natural gas plant in Ashville that will power one customer: an EdgeConneX data center next door. The Ohio Power Siting Board signed off on Nov. 19, attaching 41 conditions to the project.
The plant sits behind the meter. It will supply the adjacent data center campus as its primary power source and will never connect to the public grid. Developer PowerConneX, an affiliate of EdgeConneX, plans commercial operation as early as the second quarter of 2027, according to the company's project page.
Where Will the Plant Sit and How Will It Run?
The Ashville Energy Center will occupy 110 acres along State Route 752, east of State Route 23, in Pickaway County. Signal Ohio reported the plant will fuel two data center buildings owned by EdgeConneX. The siting board has no jurisdiction over the data centers themselves — only the power plant fell under its review.
PowerConneX filed its application on May 12, 2026, under case 26-196-EL-BGN. Site preparation was expected to begin in the third quarter of 2026, and commercial operation could start as early as Q2 2027, per the company's project page. That's an aggressive timeline by any measure. Neither the board's summary nor the company's project page names the generating technology.
What Did the Board Demand in Return?
The board adopted and modified a joint stipulation between PowerConneX, the Village of Ashville and the board's staff. It sets 41 conditions meant to limit environmental and community impacts during construction and operation. PowerConneX must also honor the financial commitments it pledged to the Ashville community.
Ashville wasn't the only item on the Nov. 19 agenda. The same meeting brought approval of the Fairfield Energy Center in Millersport, Fairfield County: 1,350 MW of gas generation plus a 1,040 MW battery storage system on 122 acres, with 36 conditions attached.
Why Did Residents Push Back?
The approval follows a local fight. Residents put a referendum on the November ballot to repeal an emergency resolution setting out a development agreement between the village and EdgeConneX. More than 80% of voters backed overturning it, Signal Ohio reported.
The company saw it differently. In regulatory filings, EdgeConneX said the vote did not have "any effect" on the gas plant or the data center, and construction is under way at the site, according to the outlet. The village council's deal is dead; the project is not.
The vote barely dented the momentum. The plant, the data centers and the construction schedule all continue on their original track, and the siting board's 41 conditions now define the project's obligations to its neighbors.
What Comes Next for Ohio's Data Center Buildout?
The decision lands as Ohio weighs how far data center growth should reach into land and power policy. A leaked draft bill reported last week would widen eminent domain authority, raising the stakes for communities sitting on land that hyperscalers want.
The Ashville model — a dedicated gas plant serving a single data center campus, off the public grid — points to where the industry is heading. If EdgeConneX hits its Q2 2027 target, expect more behind-the-meter proposals to reach the siting board, with or without local blessings.
mlq.ai (Source)
More from Rebecca Stone
Show full bio
Correspondent covering technology and product news in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.
1,329 articles