Senate passes energy bill with 150-day litigation window

Senate-approved S. 5653 would shorten federal permit lawsuits to 150 days and make data-center operators pay for dedicated transmission and existing-grid use. The House vote remains pending.

By Nathan Brooks847 words

Key takeaways

  1. The Senate passed S. 5653 by 62-33 on Nov. 19; 31 Democrats and Republicans Josh Hawley and Mike Rounds voted no.
  2. The bill would limit suits over federal approvals to 150 days and allow construction during a deficient review.
  3. FERC would implement rules charging data centers for new transmission and existing-grid use.
  4. A rejected amendment would have closed a ratepayer loophole for AI hyperscalers.
  5. Rhodium Group forecast household bills $50-$78 a year lower by 2040, excluding on-site gas generation at data centers.
Senate passes the bipartisan permitting bill 62-33, sending it to the House
Senate passes the bipartisan permitting bill 62-33, sending it to the House — AStoKo / pixabay

The U.S. Senate passed the Bipartisan American Affordability and Jobs Act, S. 5653, 62-33 on Thursday evening, Nov. 19, sending the permitting overhaul to the House after the Thanksgiving recess. Thirty-one Democrats and Republicans Josh Hawley of Missouri and Mike Rounds of South Dakota voted against it. The Senate arithmetic does not settle the House arithmetic.

The measure was led by Shelley Moore Capito (R-W.Va.) and Sheldon Whitehouse (D-R.I.) of the Environment and Public Works Committee, and Mike Lee (R-Utah) and Martin Heinrich (D-N.M.) of the Energy and Natural Resources Committee. Its scope extends beyond data centers to federal reviews for power lines, pipelines, mines, and wind and solar farms.

Reviews would move onto faster timelines under the National Environmental Policy Act, National Historic Preservation Act, Endangered Species Act, Federal Power Act and Clean Water Act. The bill would also narrow state and tribal authority to deny projects over water pollution.

What does the bill change?

S. 5653 would cut the window to sue over federal approvals to 150 days, roughly five months instead of years. Construction could continue even if a court finds a federal environmental review deficient. It also makes it harder for courts to stop work before the litigation ends.

A permit-certainty section would bar an administration from revoking issued permits, except during emergencies or under new laws or rules. Developers could sue agencies for disparate treatment under a 10-year lookback. If they prevail, they could collect 50% to 100% of expected construction costs, plus litigation costs and damages from the federal Judgment Fund.

Supporters say the measure partly answers the Trump administration's delays and blocks on wind and solar projects. It has cleared the Senate. The House has not voted.

Who pays for new transmission?

FERC would gain new authority over interstate transmission, including power to approve lines when states block or delay them. It would oversee utility transmission plans, and state regulators could refer a utility to FERC when local planning appears inefficient and overly costly.

The final text also lets utilities retain their federal right of first refusal to rebuild aging corridors, although an earlier draft would have ended that right. For data centers, the bill carries a version of the White House's ratepayer-protection pledge.

Operators would effectively pay both for new transmission built to serve them and for using the existing grid, with FERC implementing the rule. For AI hyperscalers and large data-center developers, this changes the commercial treatment of grid upgrades, not merely the permitting clock.

An updated manager's amendment that would have closed a loophole that could let AI hyperscalers avoid the ratepayer provisions was not adopted. Oregon Democrats Ron Wyden and Jeff Merkley sought votes to bar data centers from federal public lands and from the bill's permit-certainty protections. Republicans did not allow simple-majority votes on those amendments, leaving both proposals unresolved.

Who supports the compromise?

  • The White House backed the bill in a statement of administration policy this month. President Trump also endorsed it on Truth Social, according to Latitude Media, while saying he still would not approve wind turbine permits, an exception inside his broader support.
  • The American Petroleum Institute, American Clean Power Association, U.S. Chamber of Commerce and National Association of Manufacturers endorsed the measure. Edison Electric Institute and climate group Evergreen Action came aboard after recent changes.
  • The Sierra Club, Natural Resources Defense Council, a coalition of 17 Democratic-led states and the National Congress of American Indians oppose it.

Capito said, according to Roll Call: "This bill has threaded a needle the likes of which this chamber has not seen in a while." Merkley said he hoped "to have a full opportunity to address the many legitimate concerns that stakeholders have raised with this bill."

What does Rhodium expect for power bills?

Rhodium Group projected average household electricity bills would be $50 to $78 a year lower by 2040 than they otherwise would be, according to Latitude Media. That is a forecast, not a confirmed saving. The projection excludes behind-the-meter gas plants at data centers, so it does not count those facilities or their local generation.

Can the House pass the bill?

Speaker Mike Johnson (R-La.) said the bill can pass the House, and Democrats Scott Peters of California and Nikki Budzinski of Illinois have voiced support. Budzinski chairs the New Democrat Coalition, which has praised permitting reform without endorsing this draft.

Many Democrats, including Rep. Jared Huffman of California, the expected chair of the House Natural Resources Committee, want to wait for the next Congress, when Democrats will hold larger majorities. Heinrich and Whitehouse argued against delay, saying the bill needs Trump's signature to become law and serves as a floor for future Democratic goals.

The House takes the bill up after Thanksgiving. The next test is whether it preserves the transmission-cost rules and resolves the hyperscaler loophole. If the Senate text survives, permitting gets faster while more grid costs fall on data-center operators.

mlq.ai (Source)

Filed under

Share this article:

More from Nathan Brooks

Nathan Brooks

Show full bio

Senior reporter covering people, launches and day-to-day practice in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,147 articles

Read also

« Previous articleNext article »