Sharon AI completes 8,208 Nvidia B300 install in Sydney for ESDS

ESDS says all 8,208 Nvidia B300 GPUs are installed in Sydney and in final testing. Handover is expected mid-December 2026, with billing from January 2027 under a $1.25 billion take-or-pay deal.

By Sophie Lindqvist622 words

Key takeaways

  1. All 8,208 Nvidia B300 GPUs installed in Sydney; final testing under way per ESDS Nov. 21 filing
  2. Five-year contract valued at $1.25 billion; ESDS commitment about $1.26 billion over 60 months, take-or-pay
  3. Handover expected mid-December 2026, billing January 2027, later than an October go-live target
  4. ESDS estimates $30 million monthly customer billing against $21 million paid to Sharon AI; figures labeled estimates
  5. Sharon AI Q3 revenue $9.9 million; projects run-rate revenue of $400-450 million from January 2027
Sharon AI installs 8,208 Nvidia B300 GPUs for ESDS in Sydney
Sharon AI installs 8,208 Nvidia B300 GPUs for ESDS in Sydney — blickpixel / pixabay

All 8,208 Nvidia B300 GPUs are now installed in Sydney and undergoing final testing, ESDS Software Solution said in a Nov. 21 stock-exchange filing. Handover is expected in December 2026. Billing starts in January 2027. The schedule has slipped from an earlier October go-live target.

That slip is the first caveat in a story otherwise full of large numbers. The machines are in place. Revenue is not yet flowing.

Who owns what

Sharon AI, which trades on Nasdaq as SHAZ, owns the hardware and the data center capacity. ESDS, an Indian software and cloud provider, sells a managed computing service on top of the cluster to customers it has not named. The end customers remain unidentified. That gap matters, because the entire revenue projection rests on unnamed buyers.

What does the contract say?

Sharon AI announced the agreement on April 1. It valued the initial five-year contract at $1.25 billion in total contract value, with a two-year extension option for the customer. ESDS puts its own commitment at about $1.26 billion over 60 months, at a fixed rate based on GPU usage. The two companies quote slightly different figures for the same deal; neither reconciles the difference in the filing.

The commercial structure is strict. ESDS said all capacity is contracted on a take-or-pay basis, according to the Nov. 21 filing. ESDS pays whether or not it sells the compute. ESDS estimates it will bill its customers about $30 million a month and pay Sharon AI about $21 million a month. ESDS labeled both figures as estimates, not commitments. A roughly $9 million monthly spread is the thesis of the whole arrangement, and it rests on end-customer demand the company has not disclosed.

One number is firm. In May, ESDS placed a $140 million cash deposit with Sharon AI, funded by a customer advance. The deposit is refundable if Sharon AI fails to deliver, ESDS said.

What did Sharon AI report?

In its third-quarter results on Nov. 16, Sharon AI said it expects to complete commissioning, testing and Nvidia verification for two deployments in December 2026 and January 2027: the ESDS cluster and a deployment for a global technology customer it did not name. Nvidia verification is a formal gate, not a formality, and the company has not yet cleared it.

The quarter itself was small. Sharon AI reported revenue of $9.9 million for the third quarter, against about $9.6 billion of total contract value across its pipeline. It expects annualized run-rate revenue to rise from $50 million to between $400 million and $450 million in January 2027. The company presents that jump as a projection tied to billing start dates, not as booked revenue, and the B300 handover must complete first.

What is not said

Three things sit outside the filings. ESDS has not named the customers behind the $30 million monthly billing estimate, nor the customer whose advance funded the $140 million deposit. Sharon AI has not disclosed the identity of the second, unnamed global technology customer that shares the December-January verification window. And neither company has explained why the October go-live target moved by roughly two months.

What to watch

The near-term tests are concrete and dated. Mid-December handover, customer acceptance, Nvidia verification, and January billing start are all scheduled events that will confirm or refute the projections. If billing begins as planned, the $400 million run-rate claim becomes checkable against reported revenue in early 2027. Until then, the installed GPUs are hardware awaiting revenue, and the take-or-pay structure means ESDS carries the cost if the unnamed customers do not materialize at the estimated $30 million per month.

mlq.ai (Source)

Filed under

Share this article:

More from Sophie Lindqvist

Sophie Lindqvist

Show full bio

News editor covering money, funding and market shifts around Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,341 articles

Read also

« Previous article