TSMC Arizona filed a JETI application Nov. 23 for a $22.6 billion, 2nm-class fab campus in Brazos County — 3,232 acres, 2,099 jobs, and a school-tax cap it calls a 'determinative' factor against an Arizona site.
Key takeaways
- TSMC's JETI application (J0055) lists total capital investment of $22,619,235,774 and 2,099 permanent jobs at a College Station ISD site.
- The campus would build 2-nanometer or more advanced logic chips, with construction from 2027 to 2031 and a 10-year incentive period starting 2032.
- TSMC calls the JETI school-tax limitation 'a determinative and compelling factor' in choosing Texas over an Arizona parcel.
- First-year average annual salary would be $133,026, excluding bonus and allowance, per the Nov. 19 economic benefit statement.
- No land has been purchased; only nonbinding agreements exist, and TSMC has not made a final investment decision.

TSMC's US subsidiary has asked Texas for a school property-tax limitation on a proposed $22.6 billion chipmaking campus that would run 2-nanometer and more advanced processes in Brazos County — and it says the tax break will decide whether the site beats Arizona.
TSMC Arizona Corporation filed the application, numbered J0055, with the Texas Comptroller under the state's Job, Energy, Technology and Innovation (JETI) program, according to the document posted on the Comptroller's site. KBTX in Bryan-College Station reported the filing landed on Monday, Nov. 23.
The project carries a precise price tag: $22,619,235,774. An economic benefit statement in the filing, prepared by Impact DataSource and dated Nov. 19, splits that into $8.60 billion for buildings and other real property and $14.02 billion for machinery and equipment.
What does the campus actually look like on paper?
The "TSMC Texas Advanced Semiconductor Manufacturing Campus" would occupy 3,231.813 acres in College Station ISD, per the parcel list in the filing. It would house one or more front-end fabs producing leading-edge logic chips on "2-nanometer and/or more advanced process technologies" for AI, high-performance computing and mobile applications.
The schedule runs like this:
- Construction from 2027 to 2031
- 2,099 permanent jobs hired between 2028 and 2030
- First-year average annual salary of $133,026, excluding bonus and allowance
- A 10-year incentive period from 2032 to 2041
Nothing is locked down yet. Brazos County officials told KBTX the land — south of the county, generally north of Koppe Bridge Road and west of I&GN Road — has not been purchased. The filing itself notes TSMC's agents have signed only nonbinding agreements on potential land purchases.
College Station ISD must sign off on the tax limitation, and KBTX reported that approval could come as early as mid-December. County officials are also discussing a possible county tax abatement. Brazos County Manager Trevor Lansdown called the project "a potential transformational opportunity for our citizens."
Why Texas is bidding against Arizona — and Sherman
The application frames the Brazos County site as part of a competitive search for TSMC's "second campus for advanced semiconductor manufacturing expansion in the United States." The rival parcel sits in Arizona, where TSMC has operated a fab in North Phoenix since late 2024. KBTX reported that Sherman, in North Texas, is also in contention — and that TSMC has not made a final investment decision.
TSMC pulls no punches on the money. The filing calls the JETI limitation "a determinative and compelling factor" and states that without it, the Texas site "would remain at a severe competitive disadvantage."
The company attached the transcript of its Oct. 15 earnings call, in which Chairman and CEO C.C. Wei said TSMC had sent teams to Texas to evaluate sites. Wei also said the company was in talks with a customer building a fab, Terafab, about using that capacity.
Texas has leaned on the JETI program for other mega-plants recently. Tesla applied through the same mechanism for a proposed $3.1 billion polysilicon plant near Corpus Christi.
If College Station ISD approves the limitation in December and TSMC commits, Brazos County becomes the front-runner for one of the largest single private investments in the state — with 2nm wafers flowing toward AI and HPC customers from the early 2030s, while Arizona waits to learn whether its second bite at the expansion went to a rival time zone.
mlq.ai (Source)
More from Rebecca Stone
Show full bio
Correspondent covering technology and product news in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.
1,307 articles