Wallonia orders Google to halt 30,000 m² Farciennes data center work

Wallonia’s verbal stop order targets about 300 workers at Google’s Farciennes site, where a 30,000 m² building stands nearly complete and a river-water permit remains disputed.

By Sophie Lindqvist626 words

Key takeaways

  1. Nov. 26: Walloon inspectors issued a verbal stop order to about 300 workers at Google’s Farciennes site.
  2. Inspectors found a 30,000-square-meter building, described as about 3 hectares, nearly complete.
  3. The 53-hectare site has a 2024 permit for three air-cooled data centers.
  4. Desquesnes rejected the river-cooled modification in August; the Council of State hearing is set for Jan. 7.
  5. Greenpeace estimates 1 billion liters of annual cooling water at Saint-Ghislain; Google has announced €5 billion for Belgian cloud and AI infrastructure over two years.
Wallonia orders Google to stop work on its Farciennes data center
Wallonia orders Google to stop work on its Farciennes data center — wal_172619 / pixabay

On Thursday, Nov. 26, Walloon inspectors gave about 300 workers a verbal stop order at Google’s Farciennes data center, where a 30,000-square-meter building was nearly complete.

Raphaël Stokis, Wallonia’s senior planning official, sent the inspectors. He said the order would be confirmed to Google in writing. RTBF did not report whether Google complied or when written confirmation would arrive.

What did inspectors find at Farciennes?

Stokis said inspectors found a 30,000-square-meter building, described as about 3 hectares, almost complete. The Farciennes project is Google’s second Belgian data center campus, occupying a 53-hectare eco-park across Farciennes and Aiseau-Presles in Hainaut, Belgium. Google subsidiary Crystal Computing develops the site.

Google received a 2024 permit for three air-cooled data centers. It later sought permission to merge two buildings into one much larger center and cool it with water drawn from the River Sambre. The dispute concerns that modification, not the original permit.

The report does not identify the nearly finished building’s permitted design, server count or IT load. Nor does it give a completion date for the wider campus. Those omissions leave the building’s commercial scale uncertain.

Why did the river-cooled modification fail?

After the regional administration approved Google’s modification, a resident appealed, and in August, Walloon planning minister François Desquesnes refused the changed permit, citing water demand.

Desquesnes’ office said the original 2024 permit remains valid. Work matching the three smaller buildings is lawful. Building the two larger structures under the rejected modification would breach planning rules. Any violation would be reported to prosecutors.

Google appealed to Belgium’s Council of State in October. A public hearing is set for Jan. 7. Meanwhile, Desquesnes’ office said work matching the three smaller buildings can continue. Google told RTBF it was “committed to an open and collaborative dialogue with the regional government and experts” about its investments in Wallonia. That statement did not address the stop order, legal compliance or a construction schedule.

How much water is at issue?

Greenpeace Belgium said satellite images showed construction continuing on Nov. 25. It then filed an urgent complaint with Desquesnes’ office. The complaint came one day before the inspector visit.

Greenpeace spokesperson Joeri Thijs called the construction “disrespectful to the environment, local residents, and the law,” DatacenterDynamics reported. The source provides no measurement of Farciennes’ proposed water use.

Greenpeace estimates that Google’s existing Saint-Ghislain campus uses about one billion liters of water annually for cooling, returns about one quarter, and evaporates the remainder. Those figures apply to Saint-Ghislain, not Farciennes. They establish the scale of one operating campus, not the disputed project’s demand.

Google announced in 2025 that it would invest €5 billion in Belgian cloud and AI infrastructure over two years. The announcement does not specify how much money targets Farciennes. It therefore does not establish funded capacity for the halted campus.

What does this mean for Google’s expansion?

The Wallonia order follows a Nov. 24 Virginia ruling that voided Botetourt County’s approval of a Google data center and ordered construction stopped. Google also requested a grid connection for a second 1.2 GW site near Châteauroux, France. The report gives no decision on the French request.

These cases concern different jurisdictions and different approval stages. They do not quantify any common capacity effect. The Wallonia order directly affects a building already described as almost complete.

Before the Jan. 7 hearing, three questions remain: whether Google confirms the verbal order in writing, whether construction stops, and which building design the original permit covers. With the Council of State appeal pending, the nearly finished building’s permitted configuration and contribution to Belgian cloud capacity remain uncertain.

mlq.ai (Source)

Filed under

Share this article:

More from Sophie Lindqvist

Sophie Lindqvist

Show full bio

News editor covering money, funding and market shifts around Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,355 articles

Read also

« Previous articleNext article »