AI & Compute · 2 min read
XTX Markets Opens First Own Data Center: 22.5 MW in Kajaani, Finland
XTX Markets opens its first own data center in Kajaani, Finland — 22.5 MW, 15,000 sq m, over EUR 400 million invested, with 417 petabytes moved in six weeks.
Key takeaways
- XTX Markets opened its first own data center in Kajaani, Finland: 22.5 MW across 15,000 sq m and three data halls.
- The firm has invested more than EUR 400 million in Kajaani so far, COO Mike Irwin told Yle on Nov. 24.
- XTX moved 417 petabytes of storage from a leased site five kilometers away over six weeks.
- The second building is due in 2027; the third (target mid-2028) depends on permits for a 400 kV line to Otanmäki.
- The January 2025 plan calls for more than EUR 1 billion total and five data centers on a 478-acre site.

XTX Markets has opened its first company-owned data center: a 22.5 MW facility spanning 15,000 square meters and three data halls in Kajaani, northern Finland. The London-based algorithmic trading firm has sunk more than EUR 400 million into the site so far, Chief Operating Officer Mike Irwin told Finnish public broadcaster Yle on Nov. 24.
Until now, XTX rented its computing capacity from other providers. The Kajaani building changes that. Inside, the firm runs AI models that forecast prices for trading on exchanges — the first time its trading infrastructure sits on ground it owns.
Most of that EUR 400 million flowed through contracts with Finnish companies, Irwin said. The scale of the move itself was notable: XTX relocated 417 petabytes of storage from a leased site five kilometers away, and completed the transfer in six weeks, Data Phoenix reported, citing the company's announcement.
Why Kajaani, and why now?
When XTX announced the project in January 2025, it laid out an ambitious plan: more than EUR 1 billion in total investment and five data centers on a 478-acre site. The first building, now live, holds three data halls.
The cooling design leans on Finland's climate. The halls use outside air instead of water, and XTX said it is exploring giving the waste heat to the town of Kajaani free of charge — a common arrangement for Nordic data centers, where recovered heat feeds district networks.
The site already employs more than 30 full-time staff. XTX also announced EUR 1.6 million in local donations, including EUR 520,000 to Kajaani University of Applied Sciences.
What could slow the buildout?
The commercial picture hinges on power, and power hinges on permits. Grid connections are secured for the first two buildings. The second is due to start operations in 2027.
The third building is less certain. XTX is targeting mid-2028 for completion, but its power supply depends on permits for a proposed 400 kV transmission line to a substation in Otanmäki. That timeline has stretched badly.
"Where permits used to take months, they can now take years," Irwin told Yle.
The delay touches a broader constraint. Large AI and trading compute builds across Europe increasingly face grid connection queues and transmission permitting as the binding limit on expansion, not capital or land. XTX has the money and the acreage for five buildings. What it cannot control is how fast the Finnish grid arrives.
The 22.5 MW now running in Kajaani gives XTX owned infrastructure for its price-forecasting models and a template for four more buildings. Whether the remaining sites light up on schedule depends on a 400 kV line and a permitting process the company itself says now runs in years.