ASE Breaks Ground on NT$249 Billion AI Chip Testing Plant in Kaohsiung

ASE will invest NT$248.9 billion ($7.54 billion) in the K52 testing plant at Kaohsiung's Renwu park, targeting NT$117.3 billion in annual revenue and 3,300 jobs from two sites.

By Grace Kim373 words

Key takeaways

  1. ASE subsidiary Taiwan Fore Electronics will invest NT$248.9 billion (~$7.54 billion) in the J block of Kaohsiung's Renwu industrial park.
  2. Groundbreaking on the K52 plant took place Nov. 19; phased completion is set for 2028 and 2029.
  3. The J block is about 2.1 times ASE's NT$117.45 billion commitment to the adjacent K block, which broke ground in April.
  4. ASE expects the K and J blocks to generate about NT$117.3 billion in annual revenue and 3,300 jobs.
  5. CEO Tien Wu said the new AI wave has only just begun, with rising demand for high-performance chip testing.
ASE breaks ground on a NT$249 billion chip testing site in Kaohsiung, saying the AI wave has only just begun
ASE breaks ground on a NT$249 billion chip testing site in Kaohsiung, saying the AI wave has only just begun — stevepb / pixabay

ASE Technology Holding has committed NT$248.9 billion, about $7.54 billion, to a new high-end semiconductor testing complex in Kaohsiung, Taiwan, breaking ground on its K52 plant on Nov. 19.

A subsidiary, Taiwan Fore Electronics, will carry the investment in the J block of the Renwu industrial park. The figure is a planned investment announced at the groundbreaking, not a single contract. Construction is due for phased completion in 2028 and 2029.

How large is the bet?

The J block commitment is roughly 2.1 times ASE's NT$117.45 billion pledge to the neighbouring K block, which broke ground in April. Together the two sites anchor what the company calls its largest testing operation anywhere, designed around advanced testing and automation for high-performance chips.

ASE expects the K and J blocks, once running, to generate about NT$117.3 billion in annual revenue and 3,300 jobs. The company said Renwu will become its largest testing site, with its highest levels of automation and output per worker.

What did ASE say about AI demand?

"The new AI wave has only just begun," ASE chief executive Tien Wu said at the ceremony. He added that demand for high-performance chips and advanced testing will keep rising from computing and data centers.

Kaohsiung Mayor Chen Chi-mai attended the groundbreaking, underscoring the local stakes of a project that positions the southern Taiwanese city as a hub for back-end chip capacity aimed at AI workloads.

Why testing capacity matters

The investment signals where ASE sees durable demand. Front-end fabs capture most attention in the AI supply chain, but advanced packaging and testing constrain how quickly high-performance chips reach data centers. ASE's willingness to more than double its Renwu commitment within a single year indicates confidence that testing, not just wafer fabrication, will remain a bottleneck and a revenue source through the decade's second half.

The phased 2028 and 2029 completion timeline places full capacity online as AI infrastructure buildouts are expected to continue expanding, and the company's revenue projection of NT$117.3 billion a year from the two blocks gives a concrete measure of how ASE intends to convert that demand into sales.

mlq.ai (Source)

Filed under

Share this article:

More from Grace Kim

Grace Kim

Show full bio

Market editor covering people, launches and day-to-day practice in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,156 articles

Read also

« Previous articleNext article »