Bharti Airtel plans 40 MW of Assam data centre capacity

Bharti Airtel signed an Assam pact for 10 MW in Jorhat and 15 MW in Silchar, lifting planned statewide capacity to 40 MW, though investment estimates differ.

By Tom Whitfield704 words

Key takeaways

  1. The Assam-government pact was signed Wednesday, Nov. 25, for sites in Jorhat and Silchar.
  2. Jorhat: 10 MW on about four acres, ₹200 crore initial investment; Silchar: 15 MW on about five acres, ₹255 crore.
  3. The two projects are expected to create about 164 direct jobs; Bongora adds 15 MW and ₹250 crore, due by March 2028.
  4. The state puts combined capacity at 40 MW and first-phase investment at ₹705 crore across all three sites.
  5. Airtel states about ₹1,200 crore ($129.7 million); Nxtra raised $1 billion from investors including Alpha Wave Global and Carlyle.
Bharti Airtel signs Assam pact for data centres in Jorhat and Silchar
Bharti Airtel signs Assam pact for data centres in Jorhat and Silchar — u_zxva745y03 / pixabay

Bharti Airtel plans 40 MW of data centre capacity in Assam after signing a pact for facilities in Jorhat and Silchar and continuing a 15 MW build near Guwahati. The plan would place 25 MW at the two new locations, based on state figures, and would take Airtel's planned Assam footprint to 40 MW once the Bongora facility joins them. This is roadmap capacity, not live capacity; only Bongora is described as under construction.

What did the Assam pact cover?

On Wednesday, Nov. 25, Bharti Airtel and the Assam government signed a memorandum of understanding to build the two facilities. Chief Minister Himanta Biswa Sarma attended the signing. Nandita Dutta, commissioner and secretary of the state information technology department, and Priyanka Jain, Airtel's commercial circle head for Assam and the Northeast, signed for their organizations.

The pact establishes a planned program across Jorhat and Silchar. The announcement disclosed neither customer contracts nor a revenue forecast for either project. The agreement creates a development pipeline rather than operating capacity.

How much capacity and employment do the projects carry?

Sarma put Jorhat at “10 MW on about four acres” and Silchar at “15 MW on about five acres.” The state assigned ₹200 crore as the initial Jorhat investment and ₹255 crore to Silchar. Together, the two projects should create about 164 direct jobs, according to Sarma.

The 164 jobs represent an estimate, not a completed hiring count, and the state gave no schedule for filling them. These figures define the scale of the planned build, not its operating output.

How does the Bongora project fit?

At Bongora near Guwahati, Airtel is building its first Assam data centre. The state describes the 15 MW facility as under construction, with a ₹250 crore investment and a delivery date “due by March 2028.”

Adding Bongora to the two pact sites produces the state's combined figure of 40 MW. The state calls ₹705 crore the first-phase investment, equal to its separate allocations for all three locations. It therefore presents 40 MW as a pipeline spanning one construction project and two newly agreed sites.

Why do the investment estimates differ?

Airtel's own statement, reported by BusinessLine and Reuters, puts the three-site program at about ₹1,200 crore, or $129.7 million. The company assigns about ₹700 crore to Guwahati and about ₹500 crore across Jorhat and Silchar. Airtel expects all three facilities to be completed by 2028.

The state instead reports ₹705 crore for the first phase: ₹250 crore for Bongora, ₹200 crore for Jorhat and ₹255 crore for Silchar. The difference between the two published totals is ₹495 crore. The available reports do not reconcile the two totals or explain their scope.

The labels also differ: Assam calls its figure first-phase investment, while Airtel describes ₹1,200 crore as the overall plan. Without a common definition of covered spending, the lower state total cannot replace the company estimate, or the reverse. Until scope is reconciled, the project value remains uncertain.

What does Nxtra's funding provide?

Airtel operates its data centre business through its Nxtra subsidiary. Nxtra raised $1 billion this year from investors including Alpha Wave Global and Carlyle. The announcement does not earmark those funds for Assam.

That distinction matters because a corporate financing round cannot substitute for a disclosed project budget or a guaranteed commissioning schedule. The financing is substantial, but its allocation to these projects remains unspecified.

What has to happen by 2028?

Delivery, rather than the pact, now sets the timetable. Bongora faces a March 2028 deadline in the state account, while Jorhat and Silchar share the company's broader 2028 completion target. Reaching 40 MW will require all three projects to advance from their present stages, although no construction timetable was given for the two new sites.

Capacity will not count merely because a memorandum exists; Airtel must build and commission all three facilities at the stated scale. Until then, the defensible commercial view is a 40 MW Assam pipeline, not 40 MW of available capacity, with reported investment ranging from ₹705 crore to ₹1,200 crore. Progress toward March 2028 and a reconciliation of spending will determine whether Airtel's stated 40 MW becomes operating capacity.

mlq.ai (Source)

Filed under

Share this article:

More from Tom Whitfield

Tom Whitfield

Show full bio

Staff writer covering companies, deals and strategy in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,298 articles

Read also

« Previous article