Cheyenne Light files FERC agreements to wire three Microsoft data centers
Cheyenne Light filed Nov. 24 FERC agreements to wire three Microsoft data centers, with Microsoft paying up front — on top of a 590 MW Google load and a 3 GW pipeline.
Key takeaways
- Cheyenne Light filed agreements with FERC on Nov. 24 to build grid links for three Microsoft data centers, with Microsoft funding the infrastructure up front.
- A Google data center is expected to take up to 590 MW of service from late 2027, backed by a planned $1.8 billion, 564 MW gas plant.
- Cheyenne Light is working through a 3 GW data center pipeline, including 600 MW of Microsoft and Meta projects, while serving 46,000 retail customers.
- The utility proposes a mechanism to recover $686 million for two transmission projects, with Wyoming regulators expected to rule by mid-2027.
- Bright Horizon Energy was formed this month by the merger of Black Hills Corp. and NorthWestern Energy Group.

Cheyenne Light filed agreements with the Federal Energy Regulatory Commission on Nov. 24 to build distribution and transmission for three planned Microsoft data centers in Wyoming, with Microsoft paying for the infrastructure up front. Utility Dive first reported the filings. The agreements themselves are redacted, so their size and terms remain out of public view.
Microsoft will fund the wires through a contribution in aid of construction — an up-front customer payment. The utility says FERC lacks jurisdiction over these retail agreements anyway. It filed them "out of an abundance of caution," pointing to recent FERC statements on how utilities recover transmission costs for large loads. Service will run under Cheyenne Light's existing Large Power Contract Service tariff.
Why a small utility is suddenly in the data center business
Cheyenne Light serves about 46,000 retail customers. Its system set an all-time peak of 439 MW on July 20, 2026, up from 379 MW in June 2025. Yet the utility is now working through a 3 GW data center pipeline, including 600 MW of combined Microsoft and Meta projects, according to Utility Dive.
The hypervisor-scale demand lands on a grid built for a city a fraction of that size. The Microsoft filings are one piece of a much larger build in and around Cheyenne.
Cheyenne Light's parent, Bright Horizon Energy, is itself new — the holding company formed when Black Hills Corp. and NorthWestern Energy Group closed their merger this month.
What does the Google deal add?
The bigger anchor load is Google. In its third-quarter 10-Q, Black Hills said a Google data center is expected to begin taking service in late 2027 and ramp to its projected peak load by the end of 2030. Cheyenne Light expects to provide up to 590 MW of grid-connected service to the facility.
It also plans to manage roughly 2.1 GW of third-party contracted resources through a privately managed microgrid tied to the project. To supply the 590 MW, the utility intends to invest about $1.8 billion in 564 MW of new gas generation between 2027 and 2029, routed through a non-regulated affiliate.
The company flagged the concentration risk itself. It warned in the same filing that it "will have increased exposure to a single large customer."
Who pays for the transmission buildout?
Cost allocation is the live fight. Cheyenne Light has proposed a Large Customer Transmission Cost Adjustment Mechanism under which large-load customers would pay their share of transmission expansion. The utility plans to use the mechanism to recover $686 million for two transmission projects. Wyoming regulators are expected to rule by mid-2027, Utility Dive reported.
The outcome matters beyond Cheyenne. FERC's recent statements on large-load cost recovery have made utilities nervous about how they structure contracts with hyperscalers, and the "abundance of caution" filing shows even retail arrangements now get a federal paper trail.
With the Google ramp starting in late 2027, a mid-2027 state ruling on the $686 million cost mechanism, and $1.8 billion in gas generation slated for 2027 through 2029, the next 30 months will test whether a 46,000-customer utility can carry a hyperscaler load without shifting the bill onto everyone else.
mlq.ai (Source)