Northern Europe Energy secures Salaspils site for 200+ MW data center

Northern Europe Energy has secured 16 hectares in Salaspils for a planned data center campus above 200 MW, staged across 110 kV and 330 kV grid connections near Riga.

By Tom Whitfield658 words

Key takeaways

  1. The company secured exclusive rights to about 16 hectares in Salaspils, roughly 30 km southeast of Riga.
  2. Planned campus capacity exceeds 200 MW; the project remains in early planning, with no investment figure or timeline disclosed.
  3. Phase one would use the existing 110 kV network, while phase two would connect directly to adjacent 330 kV transmission lines.
  4. At more than 200 MW, the plan would be more than 20 times the stated capacity of Delska's 10 MW Riga facility.
  5. Other listed projects include 120 MW Liepāja, 400 MW Jēkabpils, 100 MW Lihula and 25 MW Juva; Riihimäki has no stated figure.
Northern Europe Energy plans a 200 MW data center outside Riga
Northern Europe Energy plans a 200 MW data center outside Riga — Akela999 / pixabay

Northern Europe Energy Group plans a data center campus of more than 200 MW after securing exclusive rights to about 16 hectares in Salaspils, roughly 30 km southeast of Riga. The land commitment is confirmed, while the capacity remains a development target; DCD reported the announcement on Monday, Nov. 23.

What has actually been secured?

The Nordic-Baltic developer holds exclusive rights to the roughly 16-hectare Salaspils site. The project remains in early planning, and the company has given no investment figure or timeline for construction and commissioning. Its more than 200 MW figure therefore describes intended capacity, not operating capacity.

Power access is defined in two stages. Phase one would draw from the existing 110 kV network. Phase two would connect directly to 330 kV transmission lines that already run alongside the site.

Thor Magnus Rovik is chief executive of Northern Europe Energy Group AS. He said: “Located just outside Riga with high-voltage grid infrastructure on its doorstep, the site is well positioned to help meet the growing demand for data center capacity across the Baltics.”

The disclosed grid sequence gives each phase a stated physical supply route rather than leaving power access undefined. It does not, however, allocate capacity between the two phases, give either phase a start date, or show when the direct 330 kV connection would enter service.

In short, the site has land and a power plan, but no announced construction date or cost.

How does Salaspils compare with current Riga capacity?

Latvia's existing data center operators cluster around Riga. Delska, SigmaNet and Standart AG operate there, and telecom company Tet already has a facility in Salaspils. The proposed campus would therefore join a market with several existing providers rather than sit outside the capital's data center cluster.

At more than 200 MW, the Salaspils plan would be far larger than Delska's 10 MW Riga facility. On the stated figures, planned Salaspils capacity is more than 20 times the Delska figure. That is a comparison of proposed scale, not evidence of customer demand, occupancy, pricing or revenue at the new site.

In practical terms, Salaspils would bring a much larger planned block of capacity into an established Riga-area market.

How large is the developer's wider pipeline?

Northern Europe Energy develops data centers, battery storage, green hydrogen and Power-to-X projects. Its disclosed data center pipeline spans Latvia, Estonia and Finland:

  • Salaspils, Latvia: more than 200 MW, in early planning.
  • Liepāja, Latvia: 120 MW.
  • Jēkabpils, Latvia: 400 MW.
  • Lihula, Estonia: 100 MW.
  • Juva, Finland: 25 MW.
  • Riihimäki, Finland: capacity not specified.

Jēkabpils has the largest stated capacity at 400 MW, while Juva has the smallest at 25 MW. The pipeline gives the developer a broad Nordic-Baltic footprint, but the figures describe projects rather than operating data centers.

The announcement does not describe these locations as operating facilities or give their individual development status. Riihimäki has no stated capacity, and the announcement gives no investment or schedule for the portfolio beyond Salaspils's early-planning status.

The company lists substantial development options, but only the Salaspils land commitment is confirmed in this announcement.

What could change the commercial picture?

The Salaspils proposal now has land rights and a two-stage grid concept. It still lacks a disclosed construction cost, schedule, phase-by-phase capacity allocation, customer commitments or date for either phase to begin operating. Those omissions leave the pace at which new capacity becomes live open to later project decisions.

The project's commercial significance comes from its location 30 km from Riga and direct access to existing high-voltage lines. If both phases proceed as described, Salaspils could add more than 200 MW of data center capacity to the market around Riga. The announcement establishes a site and a connection concept, not an operating facility. Until construction and grid energization are confirmed, however, the 200+ MW figure remains a plan rather than available capacity.

mlq.ai (Source)

Filed under

Share this article:

More from Tom Whitfield

Tom Whitfield

Show full bio

Staff writer covering companies, deals and strategy in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,236 articles

Read also

« Previous articleNext article »