Tesla unveils Powercore, a solid-state transformer for grid batteries, solar and data centers due in 2027

Hardware & Components

Tesla’s 7.4 MW Powercore transformer targets three markets

Tesla says its 7.4 MW solid-state Powercore transformer will operate in the U.S. in 2027, targeting battery storage, solar and data centers with 98.86% peak efficiency.

By
Rebecca Stone
Filed
Channel
Hardware & Components
Read
3 min read

By Rebecca Stone

Tesla rates Powercore at 7.4 MW (9 MVA) continuously at 34.5 kV, with grid-forming support for 10 MVA of peak power, and says the solid-state transformer will operate in America in 2027.

Tesla unveiled the unit Tuesday. Its Megapack account posted on X: “7.4 MW/9 MVA continuously at 34.5 kVac w/ grid-forming support for 10MVA of peak power,” and “Made in America. Operating 2027.” Powercore combines medium-voltage transformation with the inverter and breaker functions of a battery or solar site in one enclosure.

What does Tesla’s solid-state transformer combine?

  • Electrek reports peak efficiency of 98.86% and an operating range from -40°C to 55°C.
  • Electrek also reports an AC range of 10 kV to 34.5 kV and a DC range of 800 V to 2,000 V.
  • Tesla’s spec sheet, as reported by Electrek, lists system-availability guarantees of 99.9% and up, with a warranty of up to 25 years.
  • Tesla says its built-in solid-state breaker clears faults up to 1,000 times faster than a conventional breaker and uses no flammable oil, Electrek reported.

Which markets can Powercore serve?

In its Megablock storage product, Tesla uses Powercore to replace a two-step setup: Megapack inverters output 480 V AC, then a separate transformer steps up to medium voltage. Tesla says the older design had twice the losses.

For utility-scale solar, Tesla positions Powercore as a central inverter for 1,500 Vdc arrays and coming 2,000 Vdc systems, according to Electrek.

Tesla says Powercore converts medium voltage directly to 800 Vdc for data centers, the rack-power architecture Nvidia is promoting. The company also says it is working with Nvidia on 800 Vdc designs and that 10 GWh of Megapack batteries are running at data centers.

What has Tesla left undisclosed?

Tesla has not disclosed Powercore’s pricing, customers or factory location. Its U.S. pledge covers “of U.S. and imported parts,” and the announcement provides no unit-capacity or revenue target alongside the 2027 operating goal.

Tesla first said in September 2025 that it would make its own transformers when it introduced the Megapack 3 and Megablock products, Electrek reported.

How does Heron Link compare?

Heron Power, founded in 2025 by Drew Baglino, is building a competing solid-state transformer called Heron Link. Baglino left Tesla in April 2024 as senior vice president of powertrain and energy and now leads Heron.

Electrek reported three disclosed funding arrangements:

  • A $38 million Series A.
  • A $140 million Series B led by Andreessen Horowitz and Breakthrough Energy Ventures.
  • A $60 million credit facility.

Heron is building a plant in Morgan Hill, California, designed to manufacture 10,000 units a year, with commercial volume production planned for late 2027, Electrek reported.

Heron has disclosed prospective customers. Vantage Data Centers has reserved more than 1 GW and Intersect has reserved 1.5 GW, while RWE plans a pilot at a Texas battery site in April 2027, according to Electrek.

Electrek’s comparison of disclosed figures puts Powercore about 50% ahead in continuous power per unit compared with Heron Link’s roughly 5 MW. Powercore’s 98.86% efficiency is labeled peak, while Heron’s 98.6% figure carries no peak label, leaving the two efficiency measurements on different bases.

The commercial backdrop makes transformer availability increasingly important. Electrek said lead times for conventional transformers have stretched into years as data centers and renewable projects crowd interconnection queues.

What must the companies prove by 2027?

By late 2027, the contest will turn on whether Tesla turns its operating target into U.S. production and what Powercore ultimately costs, while Heron works to convert customer reservations into output from a 10,000-unit-a-year plant.

Source: mlq.ai

Share this article:

More from Rebecca Stone

Rebecca Stone

Show full bio

Correspondent covering technology and product news in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,092 articles

Related articles

« Previous article