AI & ComputeLOT 261122 · 3 min read

US Data Center Construction Costs Jump 13% in 2026, Twice the Global Rate

US data center construction costs climbed 13% in 2026, per Turner & Townsend. Silicon Valley runs $15.01 per watt; Tokyo tops the world at $18.28. Labor and grid delays drive the rise.

By Nathan Brooks535 words

Key takeaways

  1. US data center construction costs rose 13% year over year in 2026, more than twice the global rate, Turner & Townsend's index found.
  2. Silicon Valley costs $15.01 per watt for a typical 60 MW design; Dallas costs $10.51 and the US average is $12.08.
  3. 81% of 401 surveyed experts said skilled labor is constrained; 56% called power a major obstacle.
  4. Turner & Townsend's Paul Barry expects increases to moderate to 6%–10% next year.
  5. Tokyo is the world's most expensive market at $18.28 per watt.
Data center construction costs jump 13% this year as powered land and labor run short, Turner & Townsend says
Data center construction costs jump 13% this year as powered land and labor run short, Turner & Townsend says — imgix / unsplash

US data center construction costs rose 13% year over year in 2026, more than twice the global rate and roughly three times the average of the past decade, according to Turner & Townsend's annual Data Centre Construction Cost Index, reported by CNBC on Friday, Nov. 20. The project management firm attributes the jump to demand for large AI data centers outpacing the supply of powered land and construction labor.

The index, published Oct. 22, draws on more than 500 live or recently completed projects across 62 markets and a survey of roughly 400 industry experts — 401 respondents by the firm's count. That sample size gives the numbers weight. It also gives hyperscalers a bill.

What does a watt cost now?

Silicon Valley is the most expensive US market at $15.01 per watt for a typical 60 MW design, while Dallas sits at $10.51. The US country average is $12.08 per watt. At those rates, the building cost alone for a 60 MW facility runs about $900 million in Silicon Valley and about $630 million in Dallas.

Tokyo tops the global ranking at $18.28 per watt, ahead of Osaka at $17.15 and Zurich at $15.93. A Tokyo build of the same 60 MW scale would cost well over $1 billion before a single server arrives.

AI facilities carry a premium of about 10% over traditional data centers in the US, reflecting denser racks, liquid cooling and compressed schedules. The most advanced AI sites run $14 to $16 per watt, according to the index.

Why the price keeps climbing

Speed is expensive. Faster timelines push risk onto contractors and subcontractors, who build allowances for acceleration, overtime, worker attraction and higher risk fees into their prices, CNBC reported. Compressed schedules and modest margins do not coexist.

The labor picture is stark. In the survey, 81% of respondents said skilled labor in their region is constrained, with mechanical, electrical and plumbing trades the hardest to find. Just over a quarter said contractors have enough capacity to work through their backlogs. The remaining three-quarters presumably have opinions on the matter.

Power is the second bottleneck. 56% of those surveyed called it a major obstacle. Just over half said utility connections take one to two years, and almost a third said more than two years. Grid access has also become a policy fight in Texas, where ERCOT's Batch Zero review of large loads coincides with a change of governor.

What comes next

Paul Barry, Turner & Townsend's North America data center lead, told CNBC he expects cost increases to moderate to roughly 6% to 10% over the next year, since many major projects have already locked in their costs. A deceleration, to be clear — not a decline.

Demand may also shift further toward the US. On Friday, President Donald Trump said he wants to stop US companies from building data centers abroad, a position that, if enacted, would tighten domestic demand for powered land and trades already running short.

For now, the arithmetic is unforgiving: a market that must build gigawatts is paying double-digit annual increases for the privilege, and the constraint has moved from chips to concrete, copper and linemen.

mlq.ai (Source)

Filed under

Share this article:

More from Nathan Brooks

Nathan Brooks

Show full bio

Senior reporter covering people, launches and day-to-day practice in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,201 articles

Read also

« Previous article