Utilities ask FERC for 10- to 20-year data center grid contracts
FERC is weighing 10- to 20-year transmission contracts for data centers: PJM's tariff sets an 80% charge floor with 25% collateral, while California and New York ask for 15 years.
Key takeaways
- PJM transmission owners filed Nov. 16 tariffs requiring a minimum 10-year commitment of at least 80% of expected transmission charges.
- MISO proposed a three-way contract of up to 20 years; New York and California utilities proposed 15-year terms.
- PJM collateral would start at 25% of the amount owed, rise to 100% by service start, and claw back the remainder if a data center exits early.
- PG&E reports a 12.9 GW data center pipeline with no minimum term or minimum bill in its retail schedule; California's large-load tariff law targets 2028.
- FERC comments on several dockets are due Dec. 7; Southwest Power Pool must file by Nov. 20, and FERC rejected most of PJM's prior large-load plan in October.

By Rebecca Stone
A data center taking power in the PJM footprint would owe at least 80% of its expected transmission charges for a minimum of 10 years under tariffs the region's transmission owners filed with the Federal Energy Regulatory Commission on Nov. 16.
Longer commitments sit alongside it. New York and California utilities proposed 15-year terms, while grid operator MISO proposed a three-way contract of up to 20 years, according to Latitude Media's analysis of filings made on Nov. 16. The proposals answer FERC's June show-cause orders on connecting large power users. None is final: FERC must accept them, and comments on several are due Dec. 7.
What do the utilities want FERC to approve?
Each filing answers two questions: who pays for the grid upgrades, and for how long. In PJM, the answer puts the customer on the hook directly. A data center would sign a cost recovery agreement with the transmission owner and pay at least 80% of its expected transmission charges.
The money comes with collateral. A data center would post a financial guarantee starting at 25% of what it would owe, rising to the full amount by the time service begins, and would owe the remainder if it left early. PJM's transmission owners filed their own proposed tariffs covering rates, cost recovery and financial protections, Utility Dive reported.
State tariffs already exist, and Latitude Intelligence's averages — drawn from utilities whose tariffs require a transmission commitment — show the gap:
- PJM: 10 years minimum proposed federally; 12-year average state commitment
- MISO: up to 20 years; 15-year average state commitment
- California: 15 years; no state minimum
- New York: 15 years; no state minimum
Both the federal proposals and those state averages come from Latitude Media's analysis of the Nov. 16 filings. None of the federal terms has won FERC's approval.
For comparison, Dominion Energy's Virginia large-load tariff sets a floor of 85% of contracted transmission demand over 14 years, and AEP Ohio requires 85% over 12 years.
Where would the federal contract be the only commitment?
The federal contracts cover transmission only. They would not replace state retail tariffs, so a data center could end up signing two parallel sets of terms. In retail-choice states such as New Jersey and Pennsylvania, the federal agreement would become a data center's only long-term commitment to pay for transmission upgrades.
PG&E is the clearest test. The utility reports a 12.9-gigawatt data center pipeline and has no minimum term or minimum bill in its retail schedule. California passed a law in September ordering utilities to adopt large-load tariffs by 2028. New York's 15-year contract would not take effect until May 2028, leaving a data center in National Grid's Niagara Mohawk territory with no long-term commitment until then.
What's on FERC's docket?
Five filings carry the proposals:
- ER27-520: PJM transmission owners
- ER27-526: MISO
- ER27-529: New York transmission owners
- ER27-508: Southern California Edison
- ER27-513: PG&E
FERC rejected most of PJM's last large-load plan in October, in part for overreaching into retail territory. The new filings stay on transmission and leave retail rates to the states.
The sixth grid operator, Southwest Power Pool, must file by Nov. 20. Grid operators used the same deadline to propose faster connections, including PJM's plan to cut studies to about a year.
If FERC accepts the tariffs, a data center that can today walk away from a transmission build-out would instead post collateral starting at 25% of its expected charges and hold that obligation for a decade or two; the first checkpoint comes with FERC's Dec. 7 comment deadline and Southwest Power Pool's Nov. 20 filing.
mlq.ai (Source)