Fluidstack Buys 1 Million Sq Ft Prologis Warehouse for $162.9 Million
Fluidstack paid $162.9 million, about $161 per square foot, for a 1 million sq ft Prologis warehouse in Pennsylvania's Lehigh Valley, with an approved plan for a roughly 300 MW data center.
Key takeaways
- Fluidstack paid $162.9 million, about $161 per square foot, for the 1 million sq ft Lehigh Valley East 16 building, per Yardi Matrix data.
- The approved conversion plan calls for roughly 300 MW, with power from PPL Electric Utilities, a substation and closed-loop systems.
- The Allen Township Board of Supervisors approved Prologis's conversion plan unanimously in March 2025.
- Fluidstack is building data centers in Texas and New York under Anthropic's $50 billion US infrastructure plan announced in November 2025.
- Prologis is suing Trenton, Ohio to keep building a 250 MW AWS campus after voters approved a ban.

Fluidstack paid $162.9 million, about $161 per square foot, for a 1 million square foot Prologis warehouse in Pennsylvania's Lehigh Valley that it intends to convert into a data center of roughly 300 megawatts, according to Yardi Matrix data cited by Commercial Property Executive on Thursday, Nov. 26.
The property, known as Lehigh Valley East 16, sits on 85 acres at 2500 Liberty Drive near State Route 329 in Allen Township, Northampton County. The building was completed in 2023. Neither Fluidstack nor Prologis has announced the deal, and the sale date was not disclosed.
Why a logistics building became a data center site
Prologis applied earlier this year to repurpose the building and its truck parking into a hyperscale data center. The Allen Township Board of Supervisors approved the plan unanimously in March, removing the main local regulatory obstacle before the sale closed.
The warehouse's physical features fit the conversion. It has 40-foot clear heights and about 5,990 square feet of office space, and it sits about six miles from Lehigh Valley International Airport, near FedEx, DHL, Amazon and Aldi facilities. Tall clear heights give a conversion project room for rack aisles, cabling and cooling infrastructure that older stock cannot accommodate.
The location's logistics pedigree matters less than its power. The conversion plan draws electricity from PPL Electric Utilities, with a substation and closed-loop systems, Commercial Property Executive reported. The power plan, not the truck docks, is what turns a distribution shed into a compute site.
How big is 300 MW in this market?
The roughly 300 MW figure comes from Prologis's approved conversion plan, so it is a planning number rather than a commissioned capacity figure. Fluidstack has not confirmed the final build-out, and no timeline for energization has been disclosed.
The scale is consistent with the company's other projects. Fluidstack is building data centers in Texas and New York under Anthropic's $50 billion US infrastructure plan, announced in November 2025. On Nov. 25 it launched Blackbird, a modular data center design that it says scales to 400 MW and can be built within six months.
What does the deal say about the warehouse-to-data-center trade?
Prologis has been converting more of its logistics sites into data centers, and this sale shows the strategy producing revenue rather than only applications. In Ohio, the company is suing the city of Trenton to keep building a 250 MW Amazon Web Services campus after voters approved a ban on the project. The Lehigh Valley deal, by contrast, cleared local approval without a fight.
Local planning officials had pressed for detail. When the Lehigh Valley Planning Commission reviewed the project in April, its staff asked for specifics on water and electricity use, cooling and emergency response, Lehigh Valley Public Media reported. "This looks to be the first data center that might actually come to fruition in the Lehigh Valley," Commissioner Christopher Amato said at the time.
That comment points to the wider picture. Data center proposals in the region have surfaced before without being built, so a unanimous township vote and a $162.9 million purchase put this project in a different category on paper. Whether the roughly 300 MW arrives on schedule depends on grid interconnection, which remains the binding constraint for most conversions of this size.