Optical gear lead times reach 18 months as prices climb 50%
RETN reports optical network gear now taking 12 to 18 months to arrive and costing about 50% more in 2026, while remote AI sites require years of carrier planning.
Key takeaways
- Delivery times for optical network equipment rose from about 3 months to 12-15 months, with some orders at 18 months or more, RETN said.
- Optical networking equipment prices are up about 50% in 2026, according to RETN's Nov. 9 white paper.
- Carrier involvement for remote AI data center sites now starts 2-5 years before launch, up from 1-2 years, RETN said.
- A diverse circuit costs €1,800 per month versus €600 for a non-diverse circuit, RETN said.
- One hyperscaler buying Halma optical switches accounted for 22% of Halma's revenue, the company said.

Optical network equipment that used to arrive in about three months now typically takes 12 to 15 months to deliver, and some orders are taking 18 months or more, according to RETN, a network operator running fiber routes across Europe and Asia.
The price increase is nearly as steep: RETN says optical networking equipment prices rose about 50% in 2026 alone. The operator made the claim in its Nov. 9 “AI, Connected” white paper, which The Register reported on Nov. 27.
What is driving the shortage?
RETN told The Register that telcos and network operators now compete directly with AI data centers for chips and other components. Its diagnosis: the shortage is “as bad as, if not worse than, the pandemic-era shortages.”
The operator cited shortages of raw materials and skilled labor, plus energy constraints, geopolitical tensions and logistics problems. It also said carriers had compounded the shortage by postponing network upgrades to cut spending.
That timing turns fiber into a gating item for AI capacity. RETN's white paper says long lead times for specialized optical and networking equipment require teams to plan connectivity alongside compute, power and data center capacity rather than treat it as a later installation task.
Why do remote AI sites wait longer?
Developers building outside established data center clusters now need carriers involved two to five years before a site goes live, up from one to two years previously, RETN said. That engagement has to begin before opening, turning network planning into a gating item for the build.
AI data centers are moving toward remote locations such as the Nordics for land, cooler climates, power and water, according to The Register's account of RETN's findings. The catch is fiber: those areas often lack the routes needed to connect them.
Developers near cities often pay for fiber themselves, while carriers remain reluctant to build long-haul routes to serve a single site.
What does route diversity cost?
Customers now ask for four or more physically diverse routes instead of two, RETN said. The added redundancy carries a large monthly premium.
- Required routes: four or more physically diverse paths, rather than two.
- Diverse circuit: €1,800 per month.
- Non-diverse circuit: €600 per month.
The nominal route count does not guarantee independent service. RETN's white paper warns that multiple circuits or suppliers “do not necessarily provide independent infrastructure” when they share ducts, corridors or landing stations.
How does AI demand amplify the crunch?
Optical demand elsewhere in the AI supply chain is concentrating purchases. Halma said this month that one hyperscaler buying its optical switches made up 22% of its revenue. That figure shows the weight now carried by large AI buyers in optical-switch sales.
RETN, meanwhile, reports typical delivery waits of 12 to 15 months, orders stretching to 18 months or more, and price increases of roughly 50% this year. These are RETN's operator-side figures, rather than a forecast of industry-wide capacity.
Separately, the source cited U.S. moves to tighten curbs on Chinese optical transceivers for data centers. Combined with component competition, raw-material constraints, skilled-labor shortages, energy limits and logistics problems, those curbs can complicate sourcing for network operators.
For AI developers, the near-term constraint is no longer just how quickly they can secure compute. They must reserve optical equipment and fiber routes on the same multiyear timetable, then verify that supposedly diverse paths do not converge on shared ducts, corridors or landing stations.
RETN's figures point to continued commercial pressure ahead: 50% higher 2026 equipment prices, delivery windows as long as 18 months, and carrier engagement starting two to five years before a remote site opens. AI developers will have to secure scarce components and route capacity earlier if they want to hold those schedules.
mlq.ai (Source)