US data center construction starts fell 28% in the third quarter after a record spring, Cleanview says

AI & Compute

US Data Center Construction Starts Fall 28% to 8.4 GW in Q3

US data center starts fell 28% to 8.4 GW in Q3, Cleanview's satellite analysis shows, but October rebounded to 4.6 GW and 58 GW remains under construction nationwide.

By
Rebecca Stone
Filed
Channel
AI & Compute
Read
2 min read

US developers broke ground on 8.4 gigawatts of data center capacity between July and September, a 28% drop from the record 11.7 GW started in the second quarter and the first quarterly decline since early 2025, according to research firm Cleanview's November 17 analysis.

The slowdown came off a historic peak. Even after the pullback, Q3 ranked as the third-largest quarter on record and sat 55% above the same quarter of 2025, Cleanview said. Momentum returned quickly: October starts hit 4.6 GW, nearly double October 2025's figure and the second-biggest month in the dataset's history.

What Cleanview actually measured

The numbers come from satellites, not press releases. Cleanview dates a start to the month vertical construction begins — foundation and steel work, excluding land clearing — and verifies it with satellite imagery. Its dataset covers 1,338 buildings spread across 473 campuses, measuring the facility power of each building.

The quarterly picture looks like this:

  • Q2 2026: 11.7 GW started, 96 buildings
  • Q3 2026: 8.4 GW started, 65 buildings

The underlying pipeline remains on a steep climb. Developers started 38 GW in the past 12 months, twice the total of the previous 12-month window. Cleanview counts 58 GW under construction nationwide — approaching the 65 GW of capacity already operating.

Which projects carried October?

Three campuses dominated the October rebound, Cleanview said:

  • Nscale's Monarch site in West Virginia, built for Anthropic, at 720 megawatts
  • Related Digital's Stargate Michigan campus, serving Oracle and OpenAI, at 461 MW
  • Crusoe's Abilene, Texas campus, built for Microsoft, at 450 MW

The arithmetic points upward. If November and December each match October's pace, the fourth quarter would set a record of roughly 14 GW, according to Cleanview.

Why the dip? Cleanview won't say

Cleanview's newsletter did not attribute the third-quarter decline to any specific cause, an unusual restraint in a market where every wobble gets a narrative. What the firm did flag is the political weather around future projects.

Nine states — holding 41% of planned US capacity — now have a governor or governor-elect who has promised or imposed a pause on data center development, Cleanview said. Those pledges would mostly affect projects that haven't started yet, not the 58 GW already in the ground and rising.

Local signals cut both ways. Loudoun County, Virginia, the heart of the industry's established corridor, has adopted a pause on new approvals. Texas, by contrast, has resumed issuing data center permits.

What comes next

The trajectory depends less on the third quarter's dip than on whether October's rebound holds through December. With 4.6 GW started in a single month and a possible 14 GW quarter in play, Cleanview's data suggests the third-quarter decline was a breather after a record spring — while the permitting politics in nine states will shape which of the planned-but-unstarted projects ever pour concrete.

Source: mlq.ai

Share this article:

More from Rebecca Stone

Rebecca Stone

Show full bio

Correspondent covering technology and product news in Semiconductors, chip manufacturing, hardware, AI compute at Chip Dispatch.

1,131 articles

Related articles

« Previous articleNext article »